Queensland gold-development approvals

Big Vein South has moved into a live environmental-authority public notice stage.

Strategic Minerals Corporation has placed its proposed Big Vein South Gold Project into a fresh Queensland statutory milestone, with the site-specific Environmental Authority application and Progressive Rehabilitation and Closure Plan now open for public submissions from 24 September to 23 October 2026.

The proposed greenfield mine sits about 100–120 kilometres north of Richmond in North-West Queensland. Current government project information lists approximately $400 million of investment, around 980 construction jobs and 380 operational jobs, while the filed project description provides for up to 1.95 million tonnes per annum of run-of-mine ore and up to about 100,000 ounces of gold doré per year.

The commercial signal is substantial but still approval-led. A public-notice EA application is not a construction approval, final investment decision or procurement award. The next meaningful gates are the Queensland environmental decision, the Commonwealth EPBC assessment and the proponent’s own final delivery decisions.

Current stage: public submissions are open on the Queensland EA application. Construction is not yet authorised by this milestone.
BBI Project Watch artwork for the $400 million Big Vein South Gold Project showing the current environmental authority public-notice stage in North-West Queensland.
BBI Project Watch — editorial artwork. The scene is illustrative and should not be read as an official photograph, approved mine plan or final site arrangement.
Project PulseA $400 million greenfield gold project has entered a live Queensland environmental-public-notice window.
$400MProject investment
1.95 MtpaUp to ROM ore
100kozUp to gold doré / year
23 OctSubmission close
Why this stage mattersThe project is no longer sitting only in feasibility and broad approvals planning. The EA documentation is now in a defined public submission phase, giving contractors and suppliers a clearer statutory clock to watch — while still leaving major approvals ahead.

Big Vein South has entered a live Queensland EA public-notice window

The Department of the Environment, Tourism, Science and Innovation has opened public consultation on Strategic Minerals Corporation’s application for a site-specific Environmental Authority for Big Vein South. The submission period runs from 24 September until 4:30pm on 23 October 2026. The application package includes the Environmental Authority application, an Environmental Assessment Report, a Progressive Rehabilitation and Closure Plan, technical assessments and the proponent’s responses to the department’s information request.

The milestone is material because the existing environmental authority held by Strategic Minerals covers exploration and low-risk mining activity, not the full proposed construction and operation of the greenfield mine. QGold states that the new site-specific EA and Commonwealth approval under the Environment Protection and Biodiversity Conservation Act are required before the proposed full mining development can proceed.

Big Vein South was declared a prescribed project by the Queensland Government in April 2026. The Office of the Coordinator-General currently lists the project as progressing approvals, with proponent-supplied project information indicating a construction start target of Q2 2027 and construction completion in Q4 2028. Those dates remain targets rather than construction commitments.

BBI stage discipline: the confirmed development today is the live EA public-notice phase. It should not be described as final environmental approval, construction commencement or an awarded EPC/mining contract.

The filed project design outlines a complete remote mine-to-doré system

BBI project scope artwork for Big Vein South showing the proposed mine-to-gold-dore system, open cut pits, processing and remote mine infrastructure.
BBI scope intelligence — schematic only. It summarises components described in public project documentation and is not an engineering layout or approved site plan.
Proposed mine system

Three open cuts, on-site processing and remote supporting infrastructure

The Commonwealth referral describes open-cut mining from the main Big Vein South pit and two smaller satellite pits, BV1 and BV2. Mining would use conventional excavators and trucks, supported by drilling and blasting, waste-rock dumps, ore haulage and progressive rehabilitation.

Up to approximately 1.95 million tonnes per year of run-of-mine gold ore is proposed. Ore would move to the southern project area for stockpiling and processing. The project description includes both heap-leach processing in the earlier project years and a Carbon-in-Leach plant, with spent heap-leach ore later reprocessed through the CIL circuit.

Infrastructure creates multiple future work fronts — if approvals are secured

The filed design includes a CIL plant with crushing, SAG milling, carbon-in-leach, elution and a gold room; a heap-leach facility with mobile crushing, three leach pads and three ponds; a tailings storage cell; waste-rock facilities; workshops and servicing areas; warehouse and laydown; administration; water supply and mine-water systems; accommodation camps; a private airstrip; haul and access roads; and a diesel-and-solar power system.

The power concept includes diesel generation with an average load of about 8.75 MW supplemented by a 2.5 MW solar farm. The tailings storage cell is described as a lined facility with capacity for roughly 3.15 million cubic metres of settled tailings. A filter press is scheduled in the project description for later commissioning so dewatered tailings can be co-disposed with waste rock.

The EA public notice is one gate inside a broader approval pathway

Current vs next

Queensland and Commonwealth decisions are both still required

The current Queensland process concerns the site-specific Environmental Authority and associated rehabilitation planning. Public submissions can now address the application material before the department proceeds through its statutory assessment and decision-making process.

Separately, the Commonwealth EPBC portal lists the Big Vein South open-cut gold mine project as under assessment. The referral documentation describes potential clearing, groundwater drawdown and impacts that require environmental assessment. That federal process remains a distinct approval gate and should not be collapsed into the Queensland EA process.

The project already sits across four existing mining leases — ML2729, ML2739, ML90238 and ML100236 — so the central development question is not simply whether tenure exists. The focus is whether the proposed mining and infrastructure development clears the environmental and project-delivery decisions needed to proceed.

BBI approval pathway artwork for Big Vein South separating the current environmental authority public-notice stage from later Queensland and Commonwealth approvals and construction gates.
BBI approval pathway — confirmed current milestones are separated from future decisions and conditional construction activity.
Confirmed now
  • Site-specific Queensland EA application is in public-notice phase.
  • Progressive Rehabilitation and Closure Plan forms part of the application package.
  • Four existing mining leases cover the project site.
  • Commonwealth EPBC project status is under assessment.
  • Public submissions close 23 October 2026.

The proposed delivery footprint is larger than a simple open-pit mining package

Big Vein South is commercially notable because the published concept combines mining, processing and remote-site infrastructure in one greenfield development. If it proceeds, the delivery program would have to coordinate mine establishment, process facilities, power, water, tailings, roads, accommodation and aviation access in a relatively remote North-West Queensland setting.

However, BBI has not identified a current primary-source announcement of principal EPC, mining-services or major construction-package awards for the full development. Capability relevance should be treated as a forward-looking watchpoint rather than a live tender list.

Commercial lens: a $400 million project with a broad contractor interface

BBI commercial watch artwork for Big Vein South highlighting potential future capability areas across mine civils, processing, power, water, logistics and environmental work without implying confirmed package awards.
BBI commercial watch — capability areas are editorial watchpoints only. No contractor appointment or procurement package is implied.
Opportunities for industry

What contractors and suppliers should monitor

The clearest potential work fronts arise directly from the infrastructure described in the public project documents: mine civils and access, crushing and processing, SMP work around the CIL and heap-leach systems, diesel generation and solar integration, water systems, tailings infrastructure, camp and airstrip support, remote logistics, environmental monitoring and rehabilitation.

The government’s project page lists around 980 construction jobs and 380 operational jobs. Those workforce figures illustrate scale, but they do not identify package timing, procurement method or appointed contractors. The stronger commercial signal will come when approvals progress and the proponent starts releasing delivery, contracting or supplier-participation information.

For BBI readers, the practical strategy is to watch the approval clock first, then look for procurement evidence rather than assuming every design component is already contestable work.

BBI navigation Track the wider Queensland project pipeline

Follow related major-project, mining and approvals coverage as Big Vein South moves through assessment.

What to watch next

The immediate date is 23 October 2026, when the Queensland public-submission period closes. After that, industry should watch for the EA assessment outcome, movement in the Commonwealth EPBC process, any updated construction timetable and evidence of package strategy or contractor engagement.

Queensland EA public submissions close on 23 October 2026.
Departmental assessment and environmental decision.
Commonwealth EPBC assessment outcome.
Any confirmation or revision of the Q2 2027 construction target.
Principal contractor, EPC or mining-services procurement signals.
Early works, camp, roads, power, water and processing-package announcements.
Sources and verification
  1. Queensland DETSI — Big Vein South Gold EA Application (public notice and consultation; 24 September–23 October 2026).
  2. QGold / QCoal Group — Big Vein South Gold Project (project status, processing concept and lifecycle context).
  3. Australian Government EPBC Public Portal — Big Vein South open cut gold mine project (project description and assessment status).
  4. Queensland Office of the Coordinator-General — Big Vein South Gold Project (investment, jobs, prescribed-project status and proponent-supplied schedule).
Bowen Basin Index provides project, procurement and industry information based on publicly available sources. Big Vein South remains in an approvals pathway. The site-specific Environmental Authority public-notice phase does not itself constitute final environmental approval, construction approval, final investment decision, contractor appointment or procurement package release. Investment, workforce and schedule figures on the Coordinator-General project page are project information supplied by the proponent and are subject to change. References to earthworks, process plant, SMP, power, water, tailings, camp, airstrip, logistics, environmental monitoring and rehabilitation are BBI editorial capability watchpoints drawn from the published project scope and do not indicate that those packages are currently tendered or awarded. BBI artworks are illustrative and are not official project photographs, engineering drawings, approved mine plans or statutory maps.