Project Watch Major Earthworks Active North Queensland Energy Infrastructure Material Stage Change
CopperString construction milestone

Major earthworks are now underway at the $225 million Flinders Substation south of Hughenden.

CopperString has moved another major piece of infrastructure into physical construction, with crews now delivering the civil workfront for the new Flinders Substation south of Hughenden. The Queensland Government says current works include a new access road, upgrades at the Kennedy Developmental Road entrance and preparation of the future substation site, with bulk earthworks expected to be completed by the end of 2026.

The stage change matters because the Flinders Substation is one of the first major CopperString assets to move beyond approvals, design and early preparation into a sustained earthworks campaign. Powerlink previously awarded the civil and earthworks package to McCosker Contracting, while the latest government update names Wieben Earthmoving and the Warwombie Road Quarry as local businesses now winning work around the project.

For industry, the signal is real but specific: this is an active substation earthworks package within CopperString’s Eastern Link, not evidence that every transmission-line package is already under construction or available to tender.

Current position: Flinders Substation bulk earthworks are underway. The wider Eastern Link remains a staged program of design, approvals, easements, construction planning and future delivery activities.
BBI Project Watch editorial graphic for CopperString showing Flinders Substation earthworks underway near Hughenden, the $225 million substation value, McCosker earthworks and the $3.2 billion CopperString budget commitment.
BBI Project Watch — illustrative editorial graphic based on verified project information. It is not a current site photograph or an engineering drawing.
Project Pulse Flinders Substation has moved into major earthworks, converting a long-watched CopperString workfront into active construction.
$225M Flinders Substation
$3.2B State Budget Commitment
~350 km Eastern Link
End-2026 Bulk Earthworks Target
Why this stage matters CopperString has had early works, accommodation and enabling activity for some time. The material change now is that a major core asset — Flinders Substation — is in a live bulk-earthworks campaign under an awarded civil package.

Flinders Substation has moved from preparation into a live bulk-earthworks workfront

The Queensland Government’s 30 September update confirms major earthworks are underway at the Flinders Substation site, about 6 kilometres south of Hughenden. The current civil activities include construction of a new access road, works at the Kennedy Developmental Road entrance and preparation of the future substation platform.

This follows a sequence of earlier milestones. The Flinders Substation received Ministerial Infrastructure Designation approval in December 2025. In June 2026, the Government reported that ground had been broken ahead of bulk earthworks. In July, the first major package was formally identified: McCosker Contracting was awarded the Flinders Substation civil and earthworks work. The latest announcement now confirms the workfront has moved into substantive construction.

Powerlink describes the Flinders Substation as a $225 million project element. That figure is the value associated with the substation project, not the disclosed value of McCosker’s package. BBI has not identified a public contract value for the civil and earthworks award and is not treating the $225 million project figure as a contractor award.

BBI stage discipline: early works and a ceremonial ground-breaking are not the same as a sustained construction workfront. Today’s publishable change is the confirmed start of major earthworks under an awarded civil package.

The Flinders workfront sits inside the Eastern Link from Reid River to Hughenden

BBI scope graphic for CopperString Eastern Link showing Reid River, approximately 350 kilometres of 330 kilovolt transmission, Flinders Substation near Hughenden and the current civil workfront.
BBI Scope Intelligence — schematic only. It illustrates verified project components and current civil activities, not an approved transmission route map.
Eastern Link scope

Just under 350 kilometres of 330 kV transmission infrastructure, plus substations and supporting works

Powerlink’s current project page says the Eastern Link will involve just under 350 kilometres of 330 kilovolt transmission line from Reid River, near Townsville, to Hughenden. The section also requires substation sites and supporting workforce accommodation and enabling infrastructure along the delivery corridor.

The Flinders Substation is the Hughenden-side anchor now moving through construction. Powerlink says the asset is intended to feed new generation across the Flinders Shire into CopperString’s Eastern Link and connect that generation into the National Electricity Market.

The current site activities are civil rather than electrical commissioning works. Today’s verified workfront is road and access preparation, entrance upgrades and bulk earthworks for the substation site. Later substation construction and electrical installation will follow the project’s detailed delivery sequence.

The Eastern Link is targeted for completion by 2032, subject to the remaining planning and environmental approvals required for construction commencement across the wider corridor. Powerlink continues work on detailed design, easements, field investigations, environmental approvals and construction readiness while the ownership and delivery transition to a QIC-managed entity is progressed.

One substation is active; the wider Eastern Link remains staged

Confirmed now vs next gates

Earthworks underway does not mean the full transmission corridor is already in construction

The clearest way to read CopperString’s current position is to separate the live workfront from the remaining program. Confirmed today: major Flinders Substation earthworks are underway; McCosker holds the civil and earthworks package; local businesses named by Government are participating; and bulk earthworks are targeted to finish by the end of 2026.

Still ahead: completion of the civil package, progressive substation construction, ongoing Eastern Link easement and design work, remaining approvals for broader construction sections, and the implementation of the revised delivery model under the new QIC-managed ownership structure.

That distinction is commercially important. CopperString is a multi-year infrastructure program. Suppliers should not assume the current earthworks start means all future line, substation, logistics, electrical or civil packages are simultaneously open or awarded.

BBI confirmed now versus next gates graphic for CopperString showing active Flinders Substation earthworks and the remaining Eastern Link delivery steps.
BBI Delivery Position — confirmed current activity is separated from future gates so earthworks are not overstated as whole-of-program construction.
Program context: the Queensland Government has committed $3.2 billion to CopperString, including $420 million in 2026–27 for Eastern Link construction activities and enabling work connected with the Western Link. The budget commitment should not be read as the value of the current Flinders civil package.

McCosker’s package is live, local participation is visible, but Powerlink currently lists no open CopperString tenders

BBI commercial position graphic for CopperString showing active Flinders Substation construction, local supply participation and the staged Eastern Link pipeline.
BBI Commercial Position — company names reflect current public information. No additional contract value or package scope is inferred for local suppliers.
Commercial lens

The current opportunity signal is delivery participation, not a new public tender release

Powerlink’s tender and work-package page lists the Flinders Substation Civil and Earthworks Package as awarded to McCosker Contracting in July 2026. The latest government update also says Wieben Earthmoving and the Warwombie Road Quarry are winning work as construction advances.

BBI has not attributed a specific subcontract scope, award date or contract value to Wieben Earthmoving or Warwombie Road Quarry because those details are not stated in the public update. Their significance is that local supply-chain participation is now visible around an active CopperString construction workfront.

Powerlink’s current procurement page lists no open CopperString tenders or work packages. That does not mean the future pipeline is exhausted. Powerlink continues to encourage businesses to register on the CopperString supplier register and keep capability statements current so they can be considered as future opportunities develop.

Powerlink’s project page says 55 works packages had been released and 3,163 expressions of interest received by January 2026, with 876 suppliers registered. Those historic participation figures show the scale of market interest, but they should not be confused with live tender availability today.

Flinders matters because it is where CopperString starts converting policy and funding into durable network infrastructure

CopperString’s Eastern Link is designed to connect North and North West Queensland more directly to the National Electricity Market, creating a platform for new generation, firming and industrial development. The project’s wider policy case is closely tied to the North West Minerals Province and the electricity needs of mining and regional communities.

The delivery structure is also changing. A QIC-managed entity is being established to develop, deliver, own, operate and maintain CopperString, while Powerlink continues priority Eastern Link activities through the transition. For contractors, that means the near-term workfront and the long-term delivery model need to be watched separately: Powerlink is still progressing construction readiness and procurement activity, while QIC and Powerlink finalise the transition plan and operating model.

The State’s $200 million North West Energy Fund sits alongside this work and is being used to support renewable generation, batteries and microgrid solutions in the western part of the corridor. A recent memorandum of understanding for further development work around a battery and wind solution for Dugald River Mine is one example of how the transmission program and regional energy-development pipeline can intersect.

BBI previously covered the $3.2 billion CopperString budget commitment and the Dugald River mine energy-development signal. Today’s story is the construction-stage update: major earthworks are now happening at a core CopperString asset.

What contractors and suppliers should watch next

Confirmed now
  • Major earthworks are underway at Flinders Substation south of Hughenden.
  • McCosker Contracting holds the civil and earthworks package.
  • Current works include access, Kennedy Developmental Road entrance upgrades and substation site preparation.
  • Wieben Earthmoving and Warwombie Road Quarry are named as local businesses winning work.
  • Bulk earthworks are targeted for completion by the end of 2026.
  • Flinders Substation is a $225 million CopperString project element.
  • Powerlink currently lists no open CopperString tenders or work packages.
BBI Industry Directory Find Queensland capability across civil, electrical, transmission, earthworks, quarry, logistics and industrial services.

Project Watch identifies verified project movements and the commercial signals behind them. The BBI Directory helps project teams and contractors find businesses operating across regional Queensland.

Sources and primary references
  1. Queensland Government — CopperString becoming a reality in North Queensland, 30 September 2026
  2. Powerlink — CopperString project overview, status, Eastern Link and supplier information
  3. Powerlink — CopperString tenders and work packages
  4. Queensland Government — CopperString powers ahead for regional Queensland, 1 July 2026
  5. Queensland Government — 2026–27 Budget energy and CopperString investment
Disclaimer: Bowen Basin Index provides project, procurement, construction and industry information based on publicly available information reviewed to 30 September 2026. The $225 million figure is the published value of the Flinders Substation project element and is not presented as the value of McCosker Contracting’s civil and earthworks package. The $3.2 billion figure is the Queensland Government’s current CopperString budget commitment and is not one contractor award or a pool of work currently available to tender. Wieben Earthmoving and Warwombie Road Quarry are named in the Queensland Government update as local businesses winning work; BBI has not inferred package values, detailed scopes or contract structures that have not been publicly disclosed. The approximately 350-kilometre and 330-kilovolt figures describe the current Eastern Link concept from Reid River near Townsville to Hughenden. The 2032 completion target remains subject to approvals. Powerlink’s procurement page was reviewed on 30 September 2026 and listed no open CopperString tenders or work packages at that time. BBI editorial graphics are illustrative intelligence graphics only and are not official site photographs, route maps, engineering drawings, procurement documents or construction schedules.