Goldwind has been confirmed to supply 68 GW165-6.0MW turbines for Gawara Baya as the North Queensland hybrid project moves into construction.
Goldwind has confirmed its turbine package for the 408MW wind component of the Gawara Baya project, south-west of Ingham on Gugu Badhun Country. The package covers 68 GW165-6.0MW machines and puts a major named equipment supplier behind one of North Queensland’s largest renewable-energy builds.
The turbine confirmation comes after Copenhagen Infrastructure Partners acquired the project, reached final investment decision and financial close, and secured an A$1.7 billion financing facility from 10 banks. Gawara Baya combines the 408MW wind farm with a 104MW grid-forming battery energy storage system.
For contractors and suppliers, the important development is the sharpening of the delivery structure. Gawara Baya is no longer simply an approved pipeline project: early construction activities are commencing, major specialist contractors are named and the project has published a staged route from camp works and oversize-access upgrades through turbine installation, grid integration and commissioning.

The turbine package is the fresh commercial milestone
Goldwind says it will supply 68 GW165-6.0MW turbines to Gawara Baya’s 408MW wind farm. The announcement is material because it identifies the technology and supplier behind the project’s full wind-generation fleet while the project is transitioning from finance and approvals into physical delivery.
Gawara Baya had already reached a major stage change on 31 August when Copenhagen Infrastructure Partners, through Copenhagen Infrastructure V, acquired the project from Windlab, made the final investment decision and reached financial close. CIP disclosed an A$1.7 billion financing facility arranged through a consortium of 10 banks. That figure is a financing facility and should not be described as the project’s stated capital expenditure.
The underlying asset is a hybrid project: 408MW of onshore wind paired with a 104MW grid-forming battery energy storage system. The project is located about 65 kilometres south-west of Ingham and is expected to supply enough electricity for around 240,000 Australian homes when fully operational.
Gawara Baya combines large-scale wind generation with grid-forming storage

68 turbines form the wind-generation backbone
The confirmed Goldwind fleet is 68 units of the GW165-6.0MW platform. At 6MW per machine, the package corresponds to the project’s published 408MW wind capacity. The wind farm is paired with 104MW of grid-forming battery storage rather than operating as a stand-alone wind asset.
Grid-forming storage is central to the project’s system design because it can support the stability requirements of a large inverter-based renewable generator connected into the Queensland network. Public project material positions the BESS as an integrated part of Gawara Baya rather than a later add-on.
The project has also secured long-term energy offtake arrangements with Stanwell and SmartestEnergy and participates in the Australian Government’s Capacity Investment Scheme. Those arrangements provide revenue certainty while construction advances.
The delivery structure is already populated with specialist contractors
The Gawara Baya project website now identifies a delivery team managed by CIP, Windlab and Aurecon. Construction is being carried out through several specialist packages rather than one simple headline EPC appointment.
Symal Infrastructure is named for civil works. Its published scope for the project includes major civil balance-of-plant activities such as earthworks, access and internal roads, drainage, bridge works, hardstands, concrete supply and turbine foundations. Symal describes Gawara Baya as its largest Queensland project to date and says the project has received the green light to proceed.
Goldwind is now publicly confirmed for the complete 68-turbine package. Davbridge Constructions is named for road and bridge upgrades, Australian Portable Camps for workforce accommodation, Green Grid Connect for electrical works and Ampcontrol for power-conversion systems. Windlab remains actively involved in delivery support after CIP’s acquisition.
This split-package structure is commercially important. It means supply-chain access is likely to flow through multiple contract interfaces and specialist delivery partners. It also increases the importance of interface management across civil works, turbine delivery, heavy transport, electrical systems, BESS integration, workforce logistics and commissioning.
Early works begin with logistics before the full turbine build ramps up
The construction pathway is becoming more visible
The project’s current fact centre says early construction activities will commence progressively from September 2026, beginning with preparation of the accommodation-camp area. From October, the first route upgrades for oversize deliveries are scheduled to begin, while deliveries of camp components are expected from December.
Those steps matter for the turbine package because the movement of 68 large wind-turbine sets requires a coordinated logistics route, laydown strategy, foundations, crane operations and interface sequencing. Goldwind’s supplier confirmation now sits inside a real construction pathway rather than a pre-finance development schedule.
Beyond the initial enabling works, the major future gates are the ramp-up of balance-of-plant construction, turbine deliveries and installation, BESS and electrical integration, registration and testing, commissioning and the targeted move to full operations in 2030.

The contractor signal shifts from project formation to delivery execution

Large named packages are already placed, but construction creates secondary demand
The most visible primary packages are now substantially defined: project ownership and capital sit with CIP’s fund; Windlab and Aurecon are part of management and delivery; Symal is carrying major civil work; Goldwind has the turbine fleet; and specialist contractors are identified for road, bridge, electrical, accommodation and power-conversion scopes.
That does not eliminate supply-chain opportunity. A build of this scale can generate secondary demand around heavy haulage, cranage, temporary works, concrete and quarry supply, site establishment, environmental management, electrical installation, testing, communications, fuel and logistics, plant hire, workforce services and commissioning support.
The project fact centre currently estimates around 500 jobs at peak construction and more than A$200 million of regional economic value through local jobs, supply and contracting opportunities. The project has also committed to ongoing community investment and has developed its delivery framework with the Gugu Badhun People.
For contractors, the practical approach is to monitor the named package holders and authorised supplier channels rather than assume the project owner will directly procure every downstream workfront.
BBI Project Watch tracks commercial project signals. The Queensland directory helps project teams and suppliers identify relevant local capability.
What BBI is watching next
- Goldwind will supply 68 GW165-6.0MW turbines.
- Gawara Baya comprises 408MW wind plus a 104MW grid-forming BESS.
- CIP owns the project through its fund after acquiring it from Windlab.
- FID and financial close have been reached.
- A$1.7B financing facility secured through 10 banks.
- Major approvals have been received and early construction is commencing.
- Named contractors cover civil, roads/bridges, accommodation, electrical and power-conversion systems.
- Full oversize-delivery route readiness.
- Large-scale turbine component deliveries and erection sequencing.
- BESS and grid-connection integration.
- Registration, hold-point testing and commissioning.
- Any new downstream subcontract or supplier packages.
- Achievement of the targeted 2030 full-operation date.
Contractor and supplier signals to monitor
Sources and primary references
- Goldwind — company update confirming 68 GW165-6.0MW turbines for Gawara Baya
- Copenhagen Infrastructure Partners — acquisition, FID, financial close and A$1.7B financing facility
- Windlab — Gawara Baya moves into construction
- Gawara Baya — current fact centre, delivery team and construction sequencing
- Symal — Gawara Baya construction update