Major supplier package confirmed

Goldwind has been confirmed to supply 68 GW165-6.0MW turbines for Gawara Baya as the North Queensland hybrid project moves into construction.

Goldwind has confirmed its turbine package for the 408MW wind component of the Gawara Baya project, south-west of Ingham on Gugu Badhun Country. The package covers 68 GW165-6.0MW machines and puts a major named equipment supplier behind one of North Queensland’s largest renewable-energy builds.

The turbine confirmation comes after Copenhagen Infrastructure Partners acquired the project, reached final investment decision and financial close, and secured an A$1.7 billion financing facility from 10 banks. Gawara Baya combines the 408MW wind farm with a 104MW grid-forming battery energy storage system.

For contractors and suppliers, the important development is the sharpening of the delivery structure. Gawara Baya is no longer simply an approved pipeline project: early construction activities are commencing, major specialist contractors are named and the project has published a staged route from camp works and oversize-access upgrades through turbine installation, grid integration and commissioning.

Current signal: Goldwind’s 68-turbine scope is confirmed. Broader future subcontract opportunities should only be treated as live when released by CIP, Windlab, the named delivery contractors or an authorised procurement channel.
BBI Project Watch hero showing Gawara Baya in North Queensland with 68 Goldwind turbines confirmed, a 408MW wind farm, 104MW BESS and construction underway.
BBI editorial intelligence graphic. The scene is illustrative and is not an engineering layout or site plan.
Project PulseA funded hybrid wind-and-battery project now has its turbine fleet publicly confirmed as construction mobilisation advances.
68Goldwind Turbines
408MWWind Capacity
104MWGrid-forming BESS
A$1.7BFinancing Facility
Why it mattersThe Goldwind confirmation converts one of the project’s largest equipment packages from a general project assumption into a named delivery commitment: 68 turbines, a defined model and a construction program already moving on the ground.

The turbine package is the fresh commercial milestone

Goldwind says it will supply 68 GW165-6.0MW turbines to Gawara Baya’s 408MW wind farm. The announcement is material because it identifies the technology and supplier behind the project’s full wind-generation fleet while the project is transitioning from finance and approvals into physical delivery.

Gawara Baya had already reached a major stage change on 31 August when Copenhagen Infrastructure Partners, through Copenhagen Infrastructure V, acquired the project from Windlab, made the final investment decision and reached financial close. CIP disclosed an A$1.7 billion financing facility arranged through a consortium of 10 banks. That figure is a financing facility and should not be described as the project’s stated capital expenditure.

The underlying asset is a hybrid project: 408MW of onshore wind paired with a 104MW grid-forming battery energy storage system. The project is located about 65 kilometres south-west of Ingham and is expected to supply enough electricity for around 240,000 Australian homes when fully operational.

BBI accuracy note: today’s standalone development is the Goldwind turbine-supply confirmation. Financial close, ownership transfer and the financing facility are important project context, but they occurred in August and are not presented as new 24 September events.

Gawara Baya combines large-scale wind generation with grid-forming storage

BBI project system graphic for Gawara Baya showing 408MW of wind generation from 68 Goldwind turbines and a 104MW grid-forming battery energy storage system.
Project-system view — capacities are published project figures; the graphic is schematic rather than a physical site layout.
Project scope

68 turbines form the wind-generation backbone

The confirmed Goldwind fleet is 68 units of the GW165-6.0MW platform. At 6MW per machine, the package corresponds to the project’s published 408MW wind capacity. The wind farm is paired with 104MW of grid-forming battery storage rather than operating as a stand-alone wind asset.

Grid-forming storage is central to the project’s system design because it can support the stability requirements of a large inverter-based renewable generator connected into the Queensland network. Public project material positions the BESS as an integrated part of Gawara Baya rather than a later add-on.

The project has also secured long-term energy offtake arrangements with Stanwell and SmartestEnergy and participates in the Australian Government’s Capacity Investment Scheme. Those arrangements provide revenue certainty while construction advances.

The delivery structure is already populated with specialist contractors

The Gawara Baya project website now identifies a delivery team managed by CIP, Windlab and Aurecon. Construction is being carried out through several specialist packages rather than one simple headline EPC appointment.

Symal Infrastructure is named for civil works. Its published scope for the project includes major civil balance-of-plant activities such as earthworks, access and internal roads, drainage, bridge works, hardstands, concrete supply and turbine foundations. Symal describes Gawara Baya as its largest Queensland project to date and says the project has received the green light to proceed.

Goldwind is now publicly confirmed for the complete 68-turbine package. Davbridge Constructions is named for road and bridge upgrades, Australian Portable Camps for workforce accommodation, Green Grid Connect for electrical works and Ampcontrol for power-conversion systems. Windlab remains actively involved in delivery support after CIP’s acquisition.

This split-package structure is commercially important. It means supply-chain access is likely to flow through multiple contract interfaces and specialist delivery partners. It also increases the importance of interface management across civil works, turbine delivery, heavy transport, electrical systems, BESS integration, workforce logistics and commissioning.

Confirmed roles are not the same as open tenders. The named firms above are publicly identified project participants. BBI is not treating downstream crane, transport, electrical, camp, civil, commissioning or maintenance scopes as open procurement unless a responsible party releases them.

Early works begin with logistics before the full turbine build ramps up

Confirmed now vs next gates

The construction pathway is becoming more visible

The project’s current fact centre says early construction activities will commence progressively from September 2026, beginning with preparation of the accommodation-camp area. From October, the first route upgrades for oversize deliveries are scheduled to begin, while deliveries of camp components are expected from December.

Those steps matter for the turbine package because the movement of 68 large wind-turbine sets requires a coordinated logistics route, laydown strategy, foundations, crane operations and interface sequencing. Goldwind’s supplier confirmation now sits inside a real construction pathway rather than a pre-finance development schedule.

Beyond the initial enabling works, the major future gates are the ramp-up of balance-of-plant construction, turbine deliveries and installation, BESS and electrical integration, registration and testing, commissioning and the targeted move to full operations in 2030.

BBI stage pathway for Gawara Baya showing confirmed approvals, CIP ownership, A$1.7 billion financing, Goldwind turbine supply and the next delivery gates through 2030.
The A$1.7B figure shown is the financing facility disclosed by CIP, not a stated project CAPEX.

The contractor signal shifts from project formation to delivery execution

BBI commercial delivery graphic for Gawara Baya showing key project parties and contractor capability areas to watch during construction.
Capability areas are a BBI watchlist, not a statement that tenders are currently open.
Commercial position

Large named packages are already placed, but construction creates secondary demand

The most visible primary packages are now substantially defined: project ownership and capital sit with CIP’s fund; Windlab and Aurecon are part of management and delivery; Symal is carrying major civil work; Goldwind has the turbine fleet; and specialist contractors are identified for road, bridge, electrical, accommodation and power-conversion scopes.

That does not eliminate supply-chain opportunity. A build of this scale can generate secondary demand around heavy haulage, cranage, temporary works, concrete and quarry supply, site establishment, environmental management, electrical installation, testing, communications, fuel and logistics, plant hire, workforce services and commissioning support.

The project fact centre currently estimates around 500 jobs at peak construction and more than A$200 million of regional economic value through local jobs, supply and contracting opportunities. The project has also committed to ongoing community investment and has developed its delivery framework with the Gugu Badhun People.

For contractors, the practical approach is to monitor the named package holders and authorised supplier channels rather than assume the project owner will directly procure every downstream workfront.

BBI Industry DirectoryFind Queensland contractors and suppliers across civil, electrical, transport, engineering and project services.

BBI Project Watch tracks commercial project signals. The Queensland directory helps project teams and suppliers identify relevant local capability.

What BBI is watching next

Confirmed now
  • Goldwind will supply 68 GW165-6.0MW turbines.
  • Gawara Baya comprises 408MW wind plus a 104MW grid-forming BESS.
  • CIP owns the project through its fund after acquiring it from Windlab.
  • FID and financial close have been reached.
  • A$1.7B financing facility secured through 10 banks.
  • Major approvals have been received and early construction is commencing.
  • Named contractors cover civil, roads/bridges, accommodation, electrical and power-conversion systems.

Contractor and supplier signals to monitor

Heavy transport and route works
Turbine foundation and crane interfaces
Civil balance-of-plant progression
Electrical and grid packages
BESS integration and testing
Temporary facilities and camp logistics
Commissioning and operational readiness
Local supplier and First Nations enterprise opportunities
Sources and primary references
  1. Goldwind — company update confirming 68 GW165-6.0MW turbines for Gawara Baya
  2. Copenhagen Infrastructure Partners — acquisition, FID, financial close and A$1.7B financing facility
  3. Windlab — Gawara Baya moves into construction
  4. Gawara Baya — current fact centre, delivery team and construction sequencing
  5. Symal — Gawara Baya construction update
Disclaimer: Bowen Basin Index provides project, procurement, construction and industry information based on publicly available information reviewed to 24 September 2026. The confirmation that Goldwind will supply 68 GW165-6.0MW turbines is a supplier appointment for Gawara Baya’s wind-generation package. References to the A$1.7 billion amount refer to CIP’s disclosed financing facility and are not represented as the project’s stated capital expenditure. References to transport, cranage, civil works, electrical installation, logistics, commissioning, environmental services, temporary facilities and other capability areas describe commercially relevant workfronts that may arise during delivery; they do not confirm open tenders, subcontract awards or supplier opportunities unless released by the project owner, a named contractor or an authorised procurement channel. Construction sequence and the 2030 operating target remain subject to detailed execution, testing, registration and commissioning. BBI graphics are editorial intelligence illustrations and are not engineering drawings, site layouts or official procurement documents.