Passenger services opened — 9 August 2026

$1.55 billion. 6.7 kilometres. Eight new stations. Gold Coast Light Rail Stage 3 is carrying passengers as the city’s next transport infrastructure pipeline takes shape.

Passenger services on Gold Coast Light Rail Stage 3 commenced on 9 August 2026, extending the G:link south from Broadbeach South to Burleigh Heads.

The $1.549 billion project was delivered through GoldLinQ, with John Holland acting as Design & Construction contractor for the major 6.7km dual-track extension.

Eight new stations, five additional trams, new light rail and bus interchanges, depot works, pedestrian crossings, active-transport connections and public-realm upgrades formed part of the delivery program.

With Stage 3 now operational, attention is shifting toward the next Gold Coast transport projects progressing through planning, design and procurement.

Gold Coast Light Rail Stage 3 Project Watch showing the $1.55 billion project 6.7 kilometre extension eight stations and passenger services from August 2026
BBI Project Watch — Gold Coast Light Rail Stage 3 began passenger services on 9 August 2026. Some residual finishing works may continue after opening.
Project Pulse Construction → Operations
$1.549B Total Investment
6.7km Dual-Track Extension
8 New Stations
5 Additional Trams
27km Full G:link Network
Major milestone — 9 August 2026 Passenger operations are now running between Broadbeach South and Burleigh Heads, moving Gold Coast Light Rail Stage 3 from major construction into its operational phase.

The first passenger service departed Burleigh Heads on the morning of 9 August.

Stage 3 extends the existing network through Mermaid Beach, Nobby Beach and Miami before reaching the new southern terminus at Burleigh Heads.

TMR says some finishing works may continue after passenger services commence, meaning the opening should be viewed as the completion of the major delivery phase rather than an indication that every minor construction activity disappeared overnight.

$1.549B was the full Stage 3 investment

$1.549B Total Stage 3 Investment

The final TMR project profile identifies total investment of approximately $1.549 billion.

Funding comprises approximately $395.6 million from the Australian Government, $1.043 billion from the Queensland Government and $110.1 million from the City of Gold Coast.

That total includes an additional $18.6 million of ancillary works delivered in conjunction with Stage 3.

Project Snapshot
Project Gold Coast Light Rail Stage 3
Route Broadbeach South to Burleigh Heads
Length 6.7km dual-track extension
New Stations Eight
New Trams Five additional light rail vehicles
Delivery GoldLinQ
Design & Construction Contractor John Holland
Total Investment $1.549 billion
Passenger Opening 9 August 2026
Full Network Approximately 27km / 27 stations

Eight new stations now connect Broadbeach to Burleigh

Mermaid Beach
Mermaid Beach South
Nobby Beach
Miami North
Miami
Christine Avenue
Second Avenue
Burleigh Heads

John Holland’s delivered scope extended beyond track and station platforms.

The project also included new light rail and bus interchanges at Miami and Burleigh Heads, depot upgrades, pedestrian crossings, walking and cycling improvements and park upgrades along the corridor.

Stage 3 was delivered within a heavily constrained live urban environment containing traffic, businesses, utilities, pedestrians and existing communities along the Gold Coast Highway.

Illustrative Gold Coast Light Rail Stage 3 tram and station representing the completed Broadbeach South to Burleigh Heads transport project
Illustrative BBI light-rail visual. GoldLinQ delivered Stage 3 with John Holland as its Design & Construction contractor.
Major Delivery Complete

John Holland’s rail and civil delivery phase moves into close-out

Stage 3 required integration of rail systems, civil construction, station structures, underground utilities, road interfaces and urban infrastructure.

Earlier project reporting identified around 760 local jobs and very high levels of local procurement during construction.

With passenger services now operating, much of that major construction demand shifts away from Stage 3 itself and toward the next Gold Coast transport projects.

What gets built next? The Gold Coast Transport Plan has changed the pipeline

The next Gold Coast transport cycle will not simply repeat Stage 3 further south.

Queensland’s current Gold Coast Transport Plan combines light rail, bus infrastructure, major road upgrades, bridge construction, active transport and longer-term heavy-rail planning.

Gold Coast Transport Plan Major future workstreams for contractors to monitor
Light Rail GCUH → Harbour Town

Approximately 3.2km of new light rail from Gold Coast University Hospital to Biggera Waters, including three new stations, additional vehicles and depot works.

Southern Public Transport GC Surfer — Robina to Coolangatta

High-frequency metro-style services via Varsity Lakes, Burleigh Heads and Gold Coast Airport, supported by corridor and intersection infrastructure.

Central Gold Coast Nerang → Broadbeach Corridor

Metro-style services supported by six-laning sections of Nerang–Broadbeach Road, Dunlops Canal Bridge widening and intersection works.

Bridges Hope Island Road Duplication

New 236m Coombabah Creek and 194m flood-relief-channel bridges, plus intersection, shared-path and lighting works.

Active Transport Broadbeach Pedestrian Bridges

New pedestrian connections around the convention centre, casino, Pacific Fair and light rail, including a Little Tallebudgera Creek bridge.

Wider Network Coomera Connector / M1 / Airport Rail Planning

Stage 2 of the M9 is progressing through industry engagement, while M1 works and planning for heavy rail to Gold Coast Airport remain part of the wider transport program.

Pipeline-value clarification: No single combined capital value applies to the future projects identified in the Gold Coast Transport Plan. Individual projects are at different stages of planning, design, funding and procurement. Stage 3’s $1.549B value should not be interpreted as an estimate for the next light-rail extension or other future transport packages.

The former Light Rail Stage 4 is no longer the immediate southern construction pipeline

Contractors should also be aware of a fundamental change in the Gold Coast’s transport strategy.

Planning for the former light rail extension from Burleigh Heads to Coolangatta via Gold Coast Airport was stopped in September 2025 following a Queensland Government review.

There is currently no further planning for that former Stage 4 light-rail project.

The current southern strategy instead centres on the GC Surfer metro-style service between Robina and Coolangatta via Burleigh Heads and the airport, together with supporting road and intersection infrastructure.

That materially changes which contractor disciplines should be watching the southern corridor.

Contractor demand now shifts from one completed rail corridor into multiple transport modes

Stage 3 created a concentrated light-rail construction program.

The next pipeline is more fragmented, potentially spreading opportunities across rail, major civil works, bridges, road widening, bus infrastructure and active transport.

Future Capability to Watch
Contractor and supplier exposure across the next Gold Coast transport cycle
Rail systems
Track construction
Station construction
Light rail vehicles
Depot works
Bulk earthworks
Road widening
Pavements
Asphalt
Bridge construction
Marine piling
Structural concrete
Precast elements
Structural steel
Drainage
Utilities relocation
Water-main relocation
Sewer relocation
Electrical infrastructure
Traction power
Overhead wiring
Signalling
Communications
Intelligent transport systems
Traffic signals
Street lighting
Navigational lighting
Pedestrian bridges
Shared paths
Bus interchanges
Bus priority infrastructure
Airport interchange works
Traffic management
Environmental management
Surveying
Geotechnical services
Plant hire
Crane hire
Quarry materials
Concrete supply
Testing & commissioning
Rail maintenance
Procurement note: The capability areas above are not currently confirmed open packages under one Gold Coast Transport Plan tender. Different projects are progressing through different planning and procurement stages. Businesses should monitor TMR and the eventual appointed delivery teams for project-specific subcontract and supply opportunities.
Project Delivery Outlook

Stage 3 moves into operations as the next Gold Coast transport pipeline develops

GoldLinQ and John Holland have completed the major delivery phase of the $1.549 billion Stage 3 extension, with eight new stations and 6.7km of dual track now carrying passengers.

Queensland’s next Gold Coast transport program is broader than a single further light-rail extension.

Current planning includes a northern light-rail extension, metro-style public transport infrastructure across the southern and central Gold Coast, major bridge works, road widening, pedestrian infrastructure, M1 investment, Coomera Connector Stage 2 and longer-term heavy-rail planning.

The next major delivery indicators are project funding decisions, procurement models, contractor appointments and the release of downstream civil, rail, bridge and systems packages.

Near-term milestones include the Harbour Town light-rail delivery model, GC Surfer infrastructure packages, Hope Island bridge procurement, Broadbeach bridge works and progression of Coomera Connector Stage 2.

What businesses should watch next

Harbour Town light rail procurement
Harbour Town project value
Three new northern light rail stations
Additional tram procurement
Depot works
Southern GC Surfer procurement
Gold Coast Airport interchange
Robina–Miami public transport works
Nerang–Broadbeach Road widening
Dunlops Canal Bridge widening
Cocos Crescent intersection
Carrara pedestrian overpass
236m Coombabah Creek bridge
194m flood-relief bridge
Hope Island Road intersection works
Broadbeach pedestrian bridges
Little Tallebudgera Creek bridge
Coomera Connector Stage 2
M1 upgrade packages
Gold Coast Airport heavy rail planning
Major contractor appointments
Civil subcontract packages
Bridge subcontract packages
2032 delivery deadlines

Related BBI Project Watch

BBI Industry Directory

Find South East Queensland firms positioned for the next transport construction cycle

Search engineers, civil contractors, fabricators, equipment providers, maintenance businesses and project-service firms across the Gold Coast and South East Queensland.

With the $1.55B Stage 3 build now carrying passengers, which Gold Coast transport package should contractors be positioning for next — Harbour Town light rail, GC Surfer infrastructure, Hope Island bridges or the next Coomera Connector works?

Sources

  1. Department of Transport and Main Roads — Gold Coast Light Rail Stage 3
  2. Australian Government — Doors opening: first tram departs Burleigh, 7 August 2026
  3. John Holland — Gold Coast Light Rail Stage 3 opens to passengers
  4. GoldLinQ — Stage 3 opening and launch
  5. Department of Transport and Main Roads — Gold Coast Transport Plan
  6. Queensland Government — Major transport projects for the Gold Coast, 22 June 2026
  7. Department of Transport and Main Roads — Former Gold Coast Light Rail Stage 4 planning status
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information current at the date of publication. Gold Coast Light Rail Stage 3 began passenger services on 9 August 2026. TMR identifies total project investment of approximately $1.549 billion, including contributions from the Australian Government, Queensland Government and City of Gold Coast. Passenger opening does not necessarily mean every minor construction or close-out activity is complete. TMR advises that some finishing works may continue following commencement of services. GoldLinQ delivered Stage 3 with John Holland acting as its Design & Construction contractor. References to future Gold Coast Transport Plan projects do not imply that all listed projects are fully funded, tendered or under construction. The projects are at different stages of planning, design, consultation, procurement and delivery. No combined capital value is assigned to the future Gold Coast Transport Plan pipeline, and Stage 3’s $1.549 billion value should not be interpreted as an estimate for future light rail, bus, road, bridge or rail projects. Planning for the former Gold Coast Light Rail Stage 4 extension between Burleigh Heads and Coolangatta via Gold Coast Airport was stopped in September 2025. It should not be described as the current next stage of light rail construction. References to potential contractor and supplier workstreams are general observations based on publicly described future transport infrastructure. The potential workstreams identified in this article should not be interpreted as current tenders or subcontract packages. Images used in this article are BBI editorial graphics and should not be interpreted as official TMR alignment maps, engineering drawings or project photographs unless separately identified.
Project information reviewed against current TMR, Australian Government, GoldLinQ and John Holland information — 14 August 2026.