Project Watch Bowen Basin Metallurgical Coal Moranbah
EIS public submissions opened • 19 August 2026
Bowen Basin mine continuity

46 million tonnes.
15 years. One existing mine preparing for its next chapter.

Stanmore Resources’ Isaac Downs Extension has reached another major approvals milestone near Moranbah, with the project’s Environmental Impact Statement now open for public submissions.

The proposed open-cut extension could mine approximately 46 million tonnes of run-of-mine coal over 15 years, at around 2–4.5Mtpa.

But the commercially important part is not the consultation process itself.

It is what the project could do next: carry Isaac Plains Complex mining activity, workforce demand and contractor utilisation beyond the current Isaac Downs pits.

46 million tonne Isaac Downs Extension project near Moranbah targeting a 15 year mine life
BBI Project Watch — Isaac Downs Extension could continue Isaac Plains Complex mining activity for another 15 years.
Project Wire
46Mt ROM coal 15-year proposed mine life 2–4.5Mtpa ROM 15km southeast of Moranbah 100–150 construction workers 300–400 operational workforce Construction late 2027 / early 2028 First ROM coal targeted 2029 46Mt ROM coal 15-year proposed mine life 2–4.5Mtpa ROM 15km southeast of Moranbah 100–150 construction workers 300–400 operational workforce Construction late 2027 / early 2028 First ROM coal targeted 2029
Project Pulse The key story is continuity: mine life, workforce and existing infrastructure all carry forward.
46Mt ROM Coal
15 yrs Proposed Mining Life
2–4.5 Mtpa ROM
2029 First ROM Target
The real Bowen Basin story Isaac Downs is approaching the later stages of its current pits. The Extension is designed to keep the Isaac Plains Complex operating rather than force the regional mining system to start again from zero.

The project is about extending an operating mining system

Isaac Downs Extension is proposed immediately south of the existing Isaac Downs Mine, across the Isaac River and approximately 15km southeast of Moranbah.

Stanmore plans to integrate the new open-cut mine into the existing Isaac Plains Complex rather than develop an entirely standalone mining operation.

That changes the economics and contractor profile.

ROM coal would continue to move through existing mine infrastructure, including the Isaac Plains coal handling and preparation plant and established train-loading facilities.

Existing mine infrastructure areas, haul roads, water-management infrastructure, power and communications would also support the extension.

Current approvals status: the EIS entered public notification on 19 August 2026. Public submissions close on 29 September 2026. The project still requires further State and Commonwealth approvals before development can proceed.

Look at the project through four different lenses

Isaac Downs Extension means something different depending on whether the reader is looking at production, workforce, infrastructure or approvals.

Mine continuity Approximately 46Mt ROM over 15 years

Production would ramp up as the existing Isaac Downs operation winds down, targeting roughly 2–4.5Mtpa ROM and allowing mining activity at the Isaac Plains Complex to continue into its next operating phase.

Regional employment Existing workforce transitions rather than simply disappears

EIS material expects approximately 100–150 construction workers and 300–400 operational workers, with the Isaac Plains Complex workforce transitioning toward the new project as existing mining ramps down.

Brownfield advantage A new pit connected to an existing mining system

CHPP, train loading, rail loop, mine infrastructure, haul roads, water management, raw-water connections, power and communications can all support the proposed extension.

Current position EIS public notification is underway

Submissions close on 29 September 2026. Stanmore’s published pathway targets major regulatory approvals in late 2027 before construction and mining can proceed.

The transition is designed to happen before the existing pits disappear

Mining at the existing Isaac Downs Mine is expected to ramp down between 2026 and 2028.

Stanmore’s current schedule places extension construction in late 2027 or early 2028, followed by ROM coal extraction in 2029.

The timing is deliberate.

The project is intended to create a bridge between the current operating pits and the next phase of the Isaac Plains Complex.

Mine-life transition Existing operation → Extension
Indicative current project sequence
2026–28 Existing Isaac Downs mining progressively ramps down.
Late 2027 / early 2028 Extension construction currently targeted.
2029 First ROM extraction targeted.
15 years Proposed extension mining period.

That continuity is commercially important because it can preserve utilisation of existing infrastructure, workforce capability and regional supply relationships built around the Isaac Plains Complex.

Isaac Downs Extension regional context near Moranbah in Queensland's Bowen Basin
BBI regional-context graphic. Project boundaries and surrounding infrastructure are indicative editorial context rather than an official survey or approvals map.
Bowen Basin position

Around 15km southeast of Moranbah

The project sits inside one of Australia’s most established metallurgical-coal corridors.

That places it near an existing concentration of mining contractors, plant, accommodation, transport and engineering capability rather than in an undeveloped mining district.

Existing infrastructure is one of the project’s biggest advantages

Stanmore describes Isaac Downs Extension as a brownfield life-extension opportunity.

A large portion of the supporting mining system already exists.

Processing Isaac Plains CHPP ROM coal from the extension is proposed to be washed through the existing coal handling and preparation plant.
Rail Existing train loading The project can utilise the established rail loop and train-loading infrastructure serving the Isaac Plains Complex.
Mine support Shared MIA Existing mine infrastructure areas can support the extension alongside new project-specific works.
Water Water-management system Existing water infrastructure and connections form part of the integrated mine-development approach.
Utilities Power & communications The extension would connect into existing supply infrastructure rather than create an entirely isolated utilities system.
Mining system Existing equipment strategy Stanmore proposes mining methods and equipment types similar to those already used at Isaac Downs.
Infrastructure reuse does not mean no new infrastructure is required. The extension still involves a new open-cut pit and associated project works, mine establishment, roads, drainage, water-management infrastructure and connections into the existing Isaac Plains Complex.

The workforce story is unusually important

The EIS material describes the project as important to maintaining a near steady-state workforce across the Isaac Plains Complex beyond 2027 and 2028.

Construction 100–150 Approximate construction workforce identified in current project reporting.
Operations 300–400 Approximate operating workforce expected once the extension is producing.

Stanmore expects workforce arrangements to remain broadly similar to those currently used at the Isaac Plains Complex.

That includes workers living in Moranbah and other regional communities, together with mine-accommodation villages.

For local businesses, the value of a 15-year extension is therefore not only construction. It potentially preserves a longer demand profile across maintenance, transport, accommodation, equipment, fabrication, engineering and mining-support services.

Where could the next wave of contractor work sit?

The EIS does not represent these scopes as a single group of currently open tenders.

But the mine plan identifies a clear set of physical work areas that become increasingly relevant as the project approaches development.

01
Pre-strip Vegetation clearing, topsoil stripping and overburden removal ahead of mining.
02
Mine establishment ROM areas, laydown areas, supporting facilities and project setup.
03
Roads Haul roads, internal access roads and supporting transport infrastructure.
04
Water management Dams, pipelines, pumping, water transfer and operational water infrastructure.
05
Drainage Surface-water controls, channels, culverts and flood-management works.
06
Bulk earthworks Cut, fill, shaping, pads and mine-support earthworks.
07
Power Electrical distribution, connection works and supporting utilities.
08
Infrastructure modifications Changes and tie-ins required to integrate the extension with existing facilities.
09
CHPP interfaces Coal-delivery, processing and associated integration with existing plant.
10
Mining services Drilling, blasting, mining support, maintenance, logistics and operational services.
11
Survey & engineering Mine planning, civil, geotechnical, water and project-engineering support.
12
Rehabilitation Progressive rehabilitation, landform development and environmental works.
Contractor radar

New work sits around the interface between new mining areas and existing assets

The project is not a completely new processing complex.

The strongest contractor exposure is likely to sit around mine establishment, pre-strip, roads, water, drainage, utilities and integration of the extension into the existing Isaac Plains operating system.

Potential Isaac Downs Extension contractor work including pre-strip mine establishment roads water drainage earthworks power infrastructure modifications CHPP interfaces and mining services
BBI contractor-watch graphic. These are potential work areas associated with the project scope, not confirmation of currently open packages.

Public EIS submissions are an important gate — but not the final one

Public notification is one step in a wider State and Commonwealth approvals pathway.

01
EIS Terms of Reference Final requirements established for environmental assessment.
Complete
02
EIS public notification Submissions open 19 August to 29 September 2026.
Current
03
Responses & assessment Stanmore responds to submissions and the State progresses its EIS assessment.
Ahead
04
Major project approvals Mining leases, environmental authority, rehabilitation planning and Commonwealth approval remain required.
Ahead
05
Final investment & development Project development remains subject to approvals and Stanmore investment decisions.
Ahead
Confirmed project proposal
  • Approximately 46Mt ROM coal.
  • 15-year mining period.
  • Approximately 2–4.5Mtpa ROM.
  • Open-cut mining method.
  • Approximately 15km southeast of Moranbah.
  • Integration with Isaac Plains Complex.
  • Existing CHPP and train loading proposed for use.
  • Construction targeted late 2027 / early 2028.
BBI Project Watch Assessment

This is a continuity project — and that is exactly why contractors should care

Isaac Downs Extension does not need to reinvent the Isaac Plains Complex.

Its strategic value is that much of the mining system already exists.

Processing exists. Train loading exists. Water infrastructure exists. Mine-support facilities exist. A workforce and established contractor market already operate around Moranbah.

The proposed extension adds the next mining area into that operating system.

That means its commercial importance lies less in building a completely new mining precinct and more in keeping a major Bowen Basin operating platform active for another long period.

Stanmore’s current planning indicates construction in late 2027 or early 2028, followed by ROM extraction in 2029.

Before that can happen, the project still has to move through environmental assessment, major approvals and investment decisions.

For the Bowen Basin supply chain, the next major signal will be when regulatory progress begins translating into pre-strip, civil, water, infrastructure-modification and mining-service procurement.

What industry should watch next

EIS submissions close — 29 September
Stanmore response to EIS submissions
State EIS assessment report
EPBC approval pathway
Mining lease approvals
Environmental authority
Final investment decision
Construction schedule confirmation
Pre-strip procurement
Civil earthworks packages
Water-management packages
Road and haul-road works
Power connections
CHPP interface works
Mining contractor strategy
Drill-and-blast requirements
Plant mobilisation
Moranbah workforce demand
Accommodation demand
Long-term maintenance contracts
Bowen Basin question If Isaac Downs Extension proceeds, where does the strongest contractor opportunity sit?
Pre-strip & earthworks Water & drainage Mine establishment CHPP interfaces Mining services Long-term maintenance
BBI Industry Directory

Find Bowen Basin firms supporting mine development and operations

Search mining contractors, engineers, civil firms, equipment providers, fabricators and maintenance businesses across Mackay, Moranbah and Central Queensland.

Sources

  1. Queensland Government — Isaac Downs Extension project EIS
  2. Stanmore Resources — Isaac Downs Extension
  3. Stanmore — Isaac Downs Extension Initial Advice Statement
  4. Queensland DETSI — Isaac Downs Extension project information
  5. Industry Queensland — Isaac Downs Extension project hits approvals milestone, 19 August 2026
  6. Australian Government — EPBC Public Portal, Isaac Downs Extension
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information current at the date of publication. The Isaac Downs Extension is a proposed project being advanced by Stanmore ID Extension Pty Ltd, a wholly owned subsidiary of Stanmore Resources Limited. Current Queensland EIS and Stanmore project material describes the proposal as an open-cut mine extension producing approximately 46 million tonnes of run-of-mine coal over a proposed 15-year mining period, at approximately 2–4.5 million tonnes per annum. The project is proposed approximately 15 kilometres southeast of Moranbah in Queensland’s Bowen Basin. The current proposal would integrate with the existing Isaac Plains Complex and make use of existing infrastructure including the Isaac Plains coal handling and preparation plant, train-loading facilities, rail loop, mine infrastructure areas, haul roads and connections to water, power and communications. Public notification of the Environmental Impact Statement commenced on 19 August 2026 and submissions are scheduled to close on 29 September 2026. Public notification of the EIS does not constitute project approval, a final investment decision or approval to commence construction. The project remains subject to the applicable Queensland and Commonwealth environmental, mining, rehabilitation and other approval processes together with Stanmore’s internal investment decisions. Current project material targets construction for late 2027 or early 2028 and ROM coal extraction in 2029. These dates are development targets and may change as environmental assessment, approvals, engineering, project definition and investment decisions progress. Current project reporting indicates an estimated construction workforce of approximately 100–150 people and an operational workforce of approximately 300–400 people. Workforce figures are estimates and should not be interpreted as current vacancies, guaranteed employment numbers or immediate recruitment requirements. References to potential pre-strip, mine-establishment, road, water-management, drainage, earthworks, power, infrastructure-modification, CHPP-interface, engineering, rehabilitation and mining-service workstreams are based on the physical project scope and mining activities described in publicly available project material. Bowen Basin Index is not stating that each of these workstreams is currently available as an open tender or subcontract package. Actual package boundaries, procurement timing, contractor appointments, prequalification requirements and supplier opportunities will depend on final project approvals, investment decisions, engineering development and Stanmore’s eventual contracting strategy. Existing infrastructure reuse should not be interpreted as meaning the project requires no new infrastructure or construction works. BBI editorial graphics used in this article are illustrative unless specifically identified otherwise. The regional map used in this article is provided for general location context and should not be relied upon as an official mining-lease map, cadastral plan, engineering drawing, approved haul-road alignment or environmental-impact boundary. The supplied re2.jpg graphic has not been used because it contains an outdated EIS public-exhibition date that does not reflect the current August–September 2026 public-notification period. The Australian Government EPBC Public Portal currently displays some project-description figures that differ from the current Queensland EIS and Stanmore material. For this article, Bowen Basin Index has used the current State EIS / Stanmore proposal figures of approximately 46Mt ROM over 15 years at 2–4.5Mtpa.
Project information reviewed against Queensland Government, Stanmore Resources and current EIS information — 23 August 2026.