North Queensland gold processing

Mt Moss is moving from strip-out into procurement as civil and fabrication packages approach.

Sunshine Metals says refurbishment of its Mt Moss processing facility remains on track, with decommissioning of magnetite-related equipment completed, detailed engineering nearing completion and procurement of long-lead gold-processing equipment underway.

The next phase is particularly relevant to North Queensland contractors: civil and fabrication tender packages are being progressed ahead of an October–November 2026 construction start.

Mt Moss is being converted from its former magnetite configuration into a 300ktpa gold-processing hub intended initially to treat high-grade gold and silver ore from Sunshine's Liontown deposit.

This is no longer simply an acquisition story. Site strip-out is complete, equipment is being ordered and defined civil, structural and fabrication scopes are moving toward contracting.
Sunshine Metals Mt Moss gold processing facility refurbishment in North Queensland as civil and steel fabrication tender packages approach
BBI Project Watch — Sunshine Metals is advancing Mt Moss toward an October–November construction start and mid-2027 commissioning.
Project Signal Decommissioning complete, long-lead procurement underway and construction packages moving toward award.
300ktpa Existing Grinding Capacity
2 Existing Ball Mills
Oct Tender Finalisation
Oct–Nov Construction Target
Mid-27 Commissioning Target
Why this is publishable now Sunshine has moved Mt Moss into a tangible delivery window: obsolete plant has been stripped out, engineering is advanced, long-lead equipment is being procured and civil and steel-fabrication packages are moving toward finalisation.

Decommissioning is substantially complete and the site is being prepared for gold processing

Sunshine Metals says all magnetite-associated processing equipment identified for removal has now been decommissioned as it prepares the former iron-ore facility for gold processing.

Site work has included upgrades and inspections around the existing mill equipment, assessment and reconditioning of water and tailings pumps, review of site mobile plant, fuel-storage equipment, generators and electrical switchgear, and rehabilitation of roads and earthworks.

Sunshine has also recommissioned the site office complex and progressed the re-establishment of the Mt Moss accommodation camp.

Those activities are important because the development strategy is based on reusing substantial existing infrastructure rather than constructing an entirely new processing plant.

Detech Engineering is advancing the detailed gold-circuit design

Mt Moss gold processing conversion showing existing grinding circuit with new carbon in leach elution and gold room infrastructure under detailed engineering
Mt Moss is retaining much of its existing grinding infrastructure while adding the downstream gold-processing circuit required for Liontown ore.
Engineering and long-lead procurement

Existing grinding infrastructure is being tied into a new gold circuit

Detech Engineering and Sunshine have progressed detailed design for conversion of the plant, including piping and instrumentation development and definition of the new carbon-in-leach, elution and refining systems.

Procurement has already started on long-lead components, including the elution circuit and gold room.

This means the project has moved beyond conceptual design: Sunshine is now ordering equipment while preparing the remaining construction and fabrication contracts.

Civil and fabrication packages are moving toward early-October finalisation

The strongest BBI angle in the September update is the visibility Sunshine provides on its next contractor requirements.

Civil and local fabrication packages are being prepared across several defined areas of the gold-processing conversion.

Sunshine is preparing local steel-fabrication requirements associated with the carbon-in-leach circuit, including tanks, launders, platforms and related structural items.
Civil tender work includes concrete and formwork associated with foundations for the new carbon-in-leach tanks.
The fine ore bin forms part of both the civil foundation work and the steel-fabrication program being progressed ahead of construction.
Civil works include modifications and extensions around the existing mill foundations required for the refurbished processing configuration.
Existing feed hoppers, conveyors and miscellaneous structural elements are being assessed and refurbished, with this work targeted through November.
Sunshine also intends to seek supply tenders for operational inputs including fuel, cyanide and mill consumables as the facility moves toward commissioning.
BBI procurement position: these packages are based on Sunshine's identified tender and construction program. They should not be represented as awarded contracts unless Sunshine or the selected contractor confirms an award.

Mt Moss already contains the core infrastructure Sunshine wants to reuse

Sunshine completed its acquisition of 100% of the Mt Moss operation in July 2026.

The existing plant contains a grinding circuit with two ball mills and approximately 300,000 tonnes per year of capacity, together with tailings-storage infrastructure and substantial site services.

Sunshine's conversion strategy is to retain and refurbish the usable front-end infrastructure while installing the new leaching, adsorption, elution and refining systems required for gold recovery.

The site also includes workshops, offices, laydown space, accommodation and critical spares, reducing the amount of entirely new infrastructure required compared with a greenfield development.

Conversion strategy

Existing mill → new CIL circuit → elution → gold room

The former Mt Moss operation was developed around magnetite processing, but the existing grinding assets are the foundation of Sunshine's new gold-production strategy.

New downstream equipment is being added after the grinding circuit to create a conventional gold-processing flowsheet.

For contractors, this produces a refurbishment-heavy project rather than a pure greenfield build, with work spanning existing-asset rehabilitation, new structural fabrication, concrete, piping, mechanical installation, electrical integration and commissioning.

Mt Moss processing facility refurbishment scope showing existing ball mills conveyors pumps and new gold circuit civil structural and mechanical works
BBI contractor watch — Mt Moss combines existing grinding assets with new gold-circuit civil, structural, mechanical and processing infrastructure.

The earlier refurbishment estimate was $28.5 million — but September did not publish a revised total

Sunshine's April acquisition material included a preliminary costed work program for converting Mt Moss to gold processing.

That estimate totalled approximately $28.5 million, including leaching and adsorption infrastructure, grinding works, the gold room, reagent storage and general site expenses covering areas such as the camp, workshop, water and power.

The September update says Mt Moss remains on track and on budget, but it does not restate an updated total refurbishment CAPEX or disclose the value of the individual tender packages currently being prepared.

BBI cost position: $28.5 million is the earlier April 2026 preliminary refurbishment and construction estimate. BBI is not presenting it as a newly reconfirmed September budget unless Sunshine publishes an updated project cost.

Mt Moss is the processing link in Sunshine's Liontown production strategy

Mt Moss is intended initially to process high-grade gold and silver ore from Sunshine's Liontown deposit, approximately 220 kilometres from the plant.

Sunshine's current strategy links development of Liontown with refurbishment of Mt Moss, giving the company its own processing pathway rather than relying entirely on external toll treatment.

The processing hub is also around 25 kilometres from Sunshine's Sybil epithermal gold project and provides operational infrastructure that could support the company's broader North Queensland exploration portfolio.

Contractors and suppliers looking for regional capability can also browse the BBI Townsville industrial directory, while broader Queensland project activity is available through BBI Project Watch.

Confirmed now versus the next delivery gates

Confirmed now
  • Sunshine owns 100% of the Mt Moss operation.
  • Magnetite-related decommissioning has been completed.
  • Detailed gold-circuit engineering is advanced.
  • Detech Engineering is involved in the conversion design.
  • Long-lead procurement has commenced.
  • The elution circuit and gold room are among items being ordered.
  • Civil and fabrication tender packages are being progressed.
  • Construction is targeted for October–November 2026.
Mt Moss project pathway from completed decommissioning through civil and fabrication tenders October November 2026 construction commissioning and mid 2027 Liontown gold processing
BBI delivery pathway — Mt Moss is progressing from decommissioning and design into contracting, construction and ultimately mid-2027 commissioning.
Contractor watch

Early October is the next important commercial window

The project now has a relatively short runway between final design, tender completion and the targeted construction start.

Civil and fabrication awards will therefore provide the next clear signal of which local and regional contractors are moving into the Mt Moss delivery program.

BBI will also watch long-lead equipment delivery, construction mobilisation and whether Sunshine maintains its mid-2027 commissioning target.

What BBI will watch next

Early-October civil tender outcomes
CIL tank and structural fabrication awards
Fine ore bin fabrication
Fuel and cyanide supply tenders
Long-lead equipment delivery
October–November construction mobilisation
Environmental and final permitting progress
Mid-2027 commissioning and first Liontown processing
Sources and primary references
  1. Sunshine Metals — “Refurbishment on Track – Mt Moss”, ASX announcement, 8 September 2026.
  2. Sunshine Metals — Mt Moss Operation project profile.
  3. Sunshine Metals — Mt Moss acquisition and successful capital raising, 30 April 2026.
  4. Sunshine Metals — Mt Moss Acquisition Completed & Production Pathway Advanced, 2 July 2026.
  5. Mining Weekly — Mt Moss refurbishment and tender update, 8 September 2026.
  6. Industry Queensland — Mt Moss refurbishment and upcoming tenders, 8 September 2026.
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information current at the date of publication. Mt Moss remains in refurbishment and pre-construction activity and has not been represented by BBI as having completed construction or commenced gold production. Civil, steel-fabrication and supply scopes discussed in this article are based on Sunshine Metals' published project program and should not be interpreted as contract awards unless formally confirmed. Construction commencing in October–November 2026 and commissioning or first Liontown processing in mid-2027 remain current project targets and may change. The approximately $28.5 million refurbishment and construction figure referenced by BBI is an earlier April 2026 preliminary cost estimate and is not presented as a newly confirmed September project budget.