Fresh development — 14 August 2026

$10 billion. 2,400 construction jobs. One of North Queensland’s largest proposed industrial investments is moving another step toward delivery.

Townsville City Council and Quinbrook-owned project company Solquartz have signed a new Memorandum of Understanding to advance the Northern Quartz Campus at the Lansdown Eco-Industrial Precinct.

The proposal is much more than another solar project.

Northern Quartz Campus is designed as an integrated Queensland quartz-to-silicon manufacturing platform combining mineral processing, metallurgical silicon, future higher-purity silicon production, battery storage, renewable generation and major electrical infrastructure.

Queensland’s Coordinator-General currently lists the full-scale proposal at approximately $10 billion, supporting around 2,400 construction jobs and 2,000 operational jobs.

Northern Quartz Campus Project Watch showing the proposed $10 billion Townsville manufacturing precinct and 2400 construction jobs
BBI Project Watch — Northern Quartz Campus at Townsville’s Lansdown Eco-Industrial Precinct. Illustrative editorial graphic.
Project Pulse Major Manufacturing Precinct
$10B Full-Scale Investment
2,400 Construction Jobs
2,000 Operational Jobs
780MW MPS BESS Scope
515MW MPS Solar Scope
Fresh development — 14 August 2026 Townsville City Council and Solquartz have established a pathway toward a Project Development and Infrastructure Agreement targeted for completion by the end of 2026.

The proposed agreement would define Council’s infrastructure-delivery obligations and Solquartz’s contribution toward infrastructure costs associated with the project’s first stage.

It is an enabling commercial milestone rather than a main construction contract award.

The milestone is significant because the project is progressing the roads, water, electricity, approvals and commercial arrangements required before a development of this scale can move into physical delivery.

Project Snapshot
Project Northern Quartz Campus
Project Company Solquartz Pty Ltd
Sponsor Quinbrook Infrastructure Partners
Development Partner Private Energy Partners
Location Lansdown Eco-Industrial Precinct
Distance Approximately 40km south of Townsville
Queensland Status Prescribed Project
Australian Status Major Project Status
Full-Scale Investment Approximately $10 billion
Current MPS Capital Scope Up to approximately $4.5 billion
Full-Scale Construction Jobs Approximately 2,400
Full-Scale Operational Jobs Approximately 2,000

$10B full-scale vision — $4.5B current Major Project Status scope

Two major investment figures are currently associated with the Northern Quartz Campus.

They represent different scopes and should not be merged.

Project Scale Full campus versus current nationally recognised project scope
Queensland Coordinator-General $10B

Proponent-supplied full-scale investment associated with approximately 2,400 construction jobs and 2,000 operational jobs.

Australian Major Project Status Up to $4.5B

Current federally recognised project scope incorporating metallurgical silicon, biocarbon, battery storage and solar generation.

Project-value clarification: The approximately $10 billion figure represents the currently published full-scale proponent investment and should not be interpreted as the value of an awarded construction contract. The Australian Government separately identifies capital expenditure of up to approximately $4.5 billion for the current Major Project Status scope.
Illustrative Northern Quartz Campus industrial precinct at Lansdown south of Townsville showing the proposed large-scale manufacturing development
Illustrative BBI visualisation of the proposed Northern Quartz Campus. The Q4 2026 schedule displayed in the graphic reflects the current proponent-supplied timing shown by Queensland’s Coordinator-General; current project community information separately schedules construction from 2027.
Industrial Precinct

A manufacturing campus rather than a standalone plant

Northern Quartz Campus is being developed as a staged collection of interrelated processing and energy facilities.

That gives the project a significantly broader physical footprint than a conventional single-purpose manufacturing facility.

The development needs processing infrastructure, power, storage, roads, water, materials handling, utilities and long-term industrial support systems to work together.

The real strategy is to move Queensland quartz further up the value chain

The project’s strategic importance comes from what happens between raw quartz and the finished technologies that depend on silicon.

Rather than exporting the mineral and allowing most downstream value to be captured overseas, the Northern Quartz Campus aims to establish more of that manufacturing chain in Queensland.

01
Quartz Supply Australian quartz enters the manufacturing chain.
02
Feed Preparation Raw materials are unloaded, stored and conveyed.
03
Silicon Smelting Metallurgical silicon is produced in submerged-arc furnaces.
04
Higher-Purity Silicon Future downstream processing can increase product value.
05
Strategic Manufacturing Silicon supports solar, semiconductor and advanced-technology supply chains.

Quinbrook describes the development as an integrated sovereign and low-carbon solar and semiconductor supply-chain solution.

The current federal Major Project Status scope includes a 50,000tpa metallurgical-grade silicon facility and approximately 30,000tpa of biocarbon production capacity.

Solar, battery storage and high-voltage infrastructure form the power backbone

Silicon smelting is energy intensive.

That means the power system is not peripheral infrastructure — it is fundamental to the commercial model.

780MW Battery energy storage included in the current federal Major Project Status scope.
515MW Solar generation identified within the federal project scope.
275kV New network substation proposed to support Lansdown and energy-intensive industrial loads.
8hr Long-duration storage configuration associated with the proposed Supernode North BESS.
Power Infrastructure

The manufacturing strategy depends on reliable industrial-scale power

Renewable generation alone does not solve the power requirement of an energy-intensive silicon operation.

The project is therefore being developed around a combination of solar generation, long-duration battery storage and connection to Queensland’s electricity network.

That opens a major future workstream around substations, HV equipment, transmission, battery installation, cabling, control systems and commissioning.

Illustrative Northern Quartz Campus energy infrastructure with solar generation battery storage substation and high-voltage transmission
Illustrative BBI image representing the solar, battery-storage and high-voltage infrastructure proposed to support the Northern Quartz Campus.

Private Energy Partners is also progressing Lansdown Solar North and Lansdown Solar West near Woodstock.

Current project information describes those projects as primarily supporting Stage 1 of the metallurgical-silicon facility and identifies associated trackers, inverters, substations, access tracks, cabling, fencing and transmission infrastructure.

The silicon development is a major heavy-industrial construction program

The federal environmental referral gives the clearest indication of what the actual manufacturing build could involve.

The metallurgical-silicon component has a proposed disturbance footprint of approximately 95.7 hectares.

The wider concept is sized for ultimate production of up to 150,000 tonnes per year of metallurgical silicon across three 50,000tpa stages.

At that full configuration, the smelting facilities would comprise three melt shops containing three submerged-arc furnaces each — nine furnaces in total.

Publicly Described Industrial Scope

Major plant systems identified in current project documentation

Quartz unloading systems
Feedstock handling
Raw-material storage
Conveyors
Charcoal production
Three melt shops
Nine submerged-arc furnaces
Silicon handling
Product sizing
Product storage
Off-gas systems
Dust-control systems
Waste-heat systems
Wastewater systems
Electrical distribution
Instrumentation
Control systems
Plant utilities
Illustrative heavy industrial construction representing future Northern Quartz Campus steelwork cranes civil works and plant installation at Lansdown
Illustrative BBI construction visual. The Q4 2026 commencement displayed in the graphic reflects the current Coordinator-General proponent-supplied schedule; current project community information identifies 2027 as the scheduled construction commencement.
Major Construction

The physical works extend well beyond process equipment

Current federal documentation specifically identifies site establishment, excavation, earthworks, grading, compaction, stormwater infrastructure, sediment ponds, concrete works, cranage, electrical fit-out, underground services and commissioning.

That creates a potential construction market across civil, structural, mechanical, electrical and industrial-support disciplines.

Lansdown’s enabling infrastructure is integral to project delivery

Northern Quartz Campus cannot be delivered independently of the broader Lansdown Eco-Industrial Precinct.

Townsville City Council has already been advancing internal roads and other enabling infrastructure across the approximately 2,200-hectare precinct.

Council’s current Lansdown planning identifies road and raw-water infrastructure as common enabling systems required to service major proponents.

The latest Council–Solquartz agreement pathway is therefore an important commercial and infrastructure milestone.

It is intended to define who delivers key infrastructure and how the first stage contributes to those costs.

The project is moving through approvals, infrastructure and commercial milestones

March 2024 Prescribed Project Northern Quartz Campus receives Queensland prescribed-project status.
February 2026 Major Project Status Australian Government recognises the project as nationally significant.
2026 Approvals and engineering Silicon, biocarbon, BESS, solar and supporting infrastructure continue through development processes.
14 August 2026 Council–Solquartz MoU Parties establish a pathway toward the first Project Development and Infrastructure Agreement.
End-2026 target Infrastructure Agreement Council and Solquartz aim to finalise infrastructure obligations and contribution arrangements.
2027 Current community construction schedule Private Energy Partners’ current project timeline schedules construction commencement in 2027.
2029–2030 Commissioning and operations pathway Current project information targets commissioning from 2029 and commercial operation by approximately 2030.
Construction schedule clarification: Queensland’s Coordinator-General currently lists Q4 2026 as the project construction start and Q3 2029 as construction completion. That page explicitly states that the project information is supplied by the proponent and subject to change. Private Energy Partners’ current Northern Quartz Campus community timeline separately identifies construction as scheduled to commence in 2027. Taken together, the published schedules indicate that the campus is moving toward construction, while the exact commencement date remains subject to project development, approvals and proponent scheduling.

The contractor pipeline could extend across almost every major industrial discipline

Northern Quartz Campus should not be viewed as a single solar or manufacturing package.

The integrated scope combines heavy processing, civil infrastructure, power systems, renewable generation, battery storage and logistics.

Contractor Areas to Watch Capability relevant to Northern Quartz Campus and associated infrastructure
Site establishment
Bulk earthworks
Excavation
Grading & compaction
Road construction
Drainage systems
Stormwater infrastructure
Sediment ponds
Concrete foundations
Formwork
Reinforcement
Structural steel
Industrial buildings
SMP construction
Process piping
Materials handling
Conveyor systems
Feedstock storage
Furnace installation
Heavy mechanical installation
Cranes & heavy lifting
Heavy haulage
Off-gas systems
Dust collection
Industrial ventilation
Industrial electrical
HV electrical systems
275kV infrastructure
Substations
Transformers
Switchrooms
Underground cabling
Instrumentation
Control systems
Automation
Solar civil works
Solar trackers
PV installation
BESS installation
Battery containers
Transmission lines
Water infrastructure
Wastewater infrastructure
Fire systems
Laydown facilities
Temporary works
Plant hire
Fuel supply
Freight & logistics
Port logistics
Industrial supplies
Environmental services
Surveying
Geotechnical services
NDT & inspection
Testing & commissioning
Operations maintenance
Procurement note: Many of the work types above can be directly associated with infrastructure and construction activities described in current public project documentation. These capability areas should not be read as confirmation that individual tenders, subcontracts or supplier packages are currently open. Final procurement structures, EPC arrangements, contractors, package boundaries and timing should be verified through Solquartz, Quinbrook, Private Energy Partners and authorised project channels.

Sovereign manufacturing underpins the broader economic case

Northern Quartz Campus is ultimately an attempt to retain more value from Australian mineral resources before they enter global technology supply chains.

Quartz is the beginning of the silicon chain.

Metallurgical silicon and higher-purity silicon products sit much further downstream and underpin solar photovoltaics, electronics and semiconductor manufacturing.

The project therefore sits at the intersection of critical-resource development, energy infrastructure and advanced manufacturing.

That combination explains why Northern Quartz Campus has secured both Queensland prescribed-project status and Australian Government Major Project Status.

Project Delivery Outlook

The industrial opportunity extends well beyond the headline investment value

Northern Quartz Campus represents a major prospective industrial development for Townsville and the broader North Queensland supply chain.

The full-scale $10 billion investment illustrates the project’s scale, while the underlying physical scope shows how broadly future delivery could extend across industrial disciplines.

Northern Quartz Campus potentially combines heavy industrial processing, multiple furnace installations, materials handling, civil infrastructure, high-voltage power, battery storage, solar generation, transmission and long-term manufacturing operations.

The 14 August MoU does not mean thousands of construction workers are mobilising tomorrow.

It does, however, show that Council and the project are progressing another important enabling step required to move Lansdown from project planning toward physical development.

The next signals for industry will be the infrastructure agreement, final approvals, investment decisions, EPC and delivery appointments, civil mobilisation and the first substantial procurement packages.

For Townsville and North Queensland contractors and suppliers, the key value lies in tracking the project early as approvals, infrastructure agreements, delivery strategies and procurement packages continue to develop.

What businesses should watch next

Project Development and Infrastructure Agreement
End-2026 agreement target
Metallurgical silicon approvals
Biocarbon approvals
Supernode North BESS approval
Solar-project approvals
Powerlink 275kV infrastructure
Grid-connection milestones
Financial investment decisions
EPC / delivery strategy
Bulk earthworks
Road infrastructure
Raw-water infrastructure
Concrete packages
Structural steel packages
Furnace procurement
Materials-handling packages
Conveyor packages
HV electrical packages
BESS packages
Solar EPC packages
Transmission works
Heavy-lift requirements
Freight and logistics
Port supply-chain requirements
Local supplier engagement
Workforce mobilisation
Commissioning packages
Long-term maintenance services

Explore related BBI coverage

BBI Industry Directory

Find Townsville firms positioned for major industrial projects

Search engineering, fabrication, construction, electrical, automation, equipment, logistics and industrial-service businesses supporting projects across Townsville and North Queensland.

If the Northern Quartz Campus progresses into full construction, which part of the $10 billion industrial pipeline could create the strongest North Queensland contractor market — silicon processing, civil works, high-voltage infrastructure, battery storage or solar construction?

Sources

  1. Townsville City Council — TCC and Quinbrook sign MoU to progress nation-leading manufacturing precinct, 14 August 2026
  2. Queensland Coordinator-General — Northern Quartz Campus prescribed project
  3. Australian Government — Current Major Project Status projects
  4. Quinbrook Infrastructure Partners — Northern Quartz Campus
  5. Private Energy Partners — Northern Quartz Campus project and current timeline
  6. Private Energy Partners — Lansdown Solar North and Lansdown Solar West
  7. Australian Government EPBC Portal — Northern Quartz Campus Metallurgical Silicon project referral
  8. Townsville City Council — Lansdown enabling infrastructure
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information current at the date of publication. The Northern Quartz Campus remains under development and is progressing through approvals, commercial agreements, engineering, infrastructure planning and investment processes. The approximately $10 billion investment, 2,400 construction jobs, 2,000 operational jobs and Q4 2026 construction commencement currently published by Queensland’s Coordinator-General are identified by that agency as project information supplied by the proponent and subject to change. The Australian Government separately identifies capital expenditure of up to approximately $4.5 billion for the current Major Project Status scope, including a 50,000tpa metallurgical-grade silicon production facility, 30,000tpa biocarbon facility, 780MW BESS and 515MW of solar generation. Public project schedules are not fully aligned. Private Energy Partners’ current community timeline identifies construction as scheduled to commence in 2027, while the Coordinator-General page lists Q4 2026. The exact commencement date should therefore be treated as subject to change. References to contractor, subcontractor, supplier and service capability areas are general industry observations based on publicly described project infrastructure, environmental documentation and typical requirements associated with heavy industrial manufacturing, battery storage, renewable generation and major electrical infrastructure. Inclusion of a capability area does not confirm that a specific tender, subcontract or procurement package is currently open. Project capacities, capital expenditure, employment numbers, production rates, staging, procurement structures and delivery schedules may change as the project advances. Images used in this article are BBI editorial visualisations and should not be interpreted as official photographs of current Northern Quartz Campus construction or final approved project designs. Businesses should verify procurement opportunities, supplier-registration requirements and project schedules directly with Solquartz, Quinbrook Infrastructure Partners, Private Energy Partners or other authorised project channels.