Project Watch Federal Approval Mining Continuation Metallurgical Coal Dysart · Bowen Basin
Brownfield mine-life extension · Bowen Basin

A mine-life pathway to 2055.
~220ha. ~55Mt ROM. One federal approval that protects decades of operating continuity.

The Commonwealth has approved BHP Mitsubishi Alliance’s Saraji Mine Grevillea Pit Continuation Project under the Environment Protection and Biodiversity Conservation Act 1999, clearing a major federal environmental approval gate for continued open-cut mining east of the existing Grevillea Pit.

The approved action extends mining beyond ML 1782 into the approximately 220-hectare ML 700021 footprint near Dysart in Queensland’s Bowen Basin, with BMA’s project documentation identifying an operating horizon through to approximately FY2055.

BMA estimates the continuation area will provide approximately 55 million tonnes of run-of-mine metallurgical coal. Importantly, the project is designed to sustain Saraji’s existing production rather than increase annual product output.

Saraji opened in 1972. The commercial story here is not a one-off construction boom — it is the preservation of an operating platform that can keep generating mine-planning, fleet, reliability, civil, water, environmental and rehabilitation work for decades.
BMA Saraji Grevillea Pit Continuation Project federal approval showing mining to 2055, 220 hectare continuation area and 55Mt run of mine metallurgical coal
BBI Project Watch editorial artwork — Grevillea is a brownfield continuation of existing Saraji open-cut operations, not a new standalone mine.
Approval Secured
The Commonwealth approval has been granted with conditions. For the supply chain, the key consequence is production continuity — not an immediate uplift in annual product output.
Project Wire
Federal approval secured EPBC 2023/09757 ~220ha continuation footprint ~55Mt ROM metallurgical coal Mining horizon to FY2055 No increase to annual product output Existing CHPP retained Existing train load-out retained Water + rehabilitation remain central Federal approval secured EPBC 2023/09757 ~220ha continuation footprint ~55Mt ROM metallurgical coal Mining horizon to FY2055 No increase to annual product output Existing CHPP retained Existing train load-out retained Water + rehabilitation remain central
Project Pulse Grevillea is a sustaining-life project: its value is the operating base it preserves — and the recurring work required to keep that base productive, reliable and compliant.
2055 Project Horizon
220ha Continuation Area
55Mt Estimated ROM Coal
~16Mtpa Existing Mine ROM Scale
50:50 BHP · Mitsubishi
BBI Continuity View This approval is best understood on a long timeline: established mine → approval gate cleared → continuing operating horizon.
Brownfield continuity
1972 Saraji opens An established Bowen Basin metallurgical-coal operation develops around large-scale open-cut mining and supporting infrastructure.
September 2026 Grevillea approved The Commonwealth approval removes a major environmental approval gate for the continuation footprint in ML700021, subject to conditions.
Approx. FY2055 Planning horizon BMA’s project material identifies an operating horizon to around FY2055. This is a planning horizon, not a guarantee of uninterrupted production.
Why this approval matters For the Bowen Basin supply chain, the commercial signal is not a sudden greenfield construction boom. It is the preservation of a large operating base — and the maintenance, engineering, water, civil, equipment, rehabilitation and mine-services demand that comes with keeping that base productive to 2055.
Interactive · Brownfield anatomy Click through the project from four different commercial angles
Mine-front change The continuation advances the Grevillea mining footprint east into ML700021.
MiningPit progressionMining sequence, benches, ramps and active pit areas extend into the continuation lease.
EarthworksRoads + spoil + padsHaul roads, spoil areas, access and earth-moving support areas can move with the mine front.
ServicesWater + power relocationsDams, drains, pipelines, flood protection, electrical lines and substations remain relevant as the footprint advances.
Existing platform The project is designed to keep using the major operating systems Saraji already has.
ProcessingCHPP + stockpilesCoal continues through established Saraji processing and stockpile infrastructure.
LogisticsTrain load-out + railThe existing product-handling and rail interface remains part of the operating chain.
Site supportWorkshops + roads + utilitiesEstablished maintenance, access, water and electrical systems continue to support production.
Contractor duration The strongest signal is recurring sustaining work across an established mine — not one headline EPC contract.
ReliabilityPlant + mobile equipmentMechanical, structural, electrical, shutdown, field-service and component support remain recurring needs.
Mine servicesDrill + blast + surveyCore production-support activities continue as mining progresses through new ground.
ComplianceWater + environment + rehabMonitoring, rehabilitation, water management and approval-condition delivery remain long-duration workstreams.
Commercial triggers Watch the operating plan, not just the approval headline.
MobilisationWhen does ML700021 ramp up?Detailed mine-sequence timing is the clearest signal for supporting civil, infrastructure and mine-services activity.
Sustaining capitalWhat gets relocated or upgraded?Roads, power, water, plant reliability and mine-support works can create specific packages as plans mature.
ProcurementWhen do scopes become real?Only BMA or an authorised procurement channel can confirm live packages, tenders and supplier opportunities.

From referral to approval: the Commonwealth pathway behind Grevillea

BMA referred the Grevillea Pit Continuation Project to the Commonwealth in December 2023. In June 2024, the project was determined to be a controlled action under the EPBC Act because of potential impacts to listed threatened species and ecological communities and to water resources associated with a large coal mining development.

The project was assessed through preliminary documentation, supported by terrestrial ecology, surface-water, groundwater, groundwater-dependent ecosystem, rehabilitation, offset and management-plan material.

Dec 2023 EPBC referral lodged BMA refers the Grevillea continuation to the Commonwealth under EPBC reference 2023/09757.
Jun 2024 Controlled action Threatened species/communities and water resources become the controlling Commonwealth matters.
2024–26 Technical assessment Ecology, groundwater, surface water, offsets, rehabilitation and IESC scientific advice inform the assessment.
Sep 2026 Approved with conditions The Commonwealth decision gives BMA the federal environmental approval required for the continuation project.
Approval clarification: federal environmental approval is an important project gate, but it does not remove BMA’s obligation to comply with the approval conditions, existing Queensland Environmental Authority requirements, water-management obligations, rehabilitation commitments and other applicable approvals.
BBI map graphic showing Saraji Mine Grevillea Pit extending east from ML1782 into the 220 hectare ML700021 continuation area north of Dysart
BBI location artwork — the continuation extends the existing Grevillea mining footprint east from ML1782 into ML700021.
A 220ha brownfield step

The physical change is concentrated at the mine front — not across the whole Saraji system

The project area covers approximately 220 hectares and comprises ML700021 immediately east of current Saraji operations in ML1782.

BMA’s documentation places the project between Spring Creek to the north and Phillips Creek to the south, with existing high-voltage power easements further east.

That geography is commercially important: Grevillea can feed into Saraji’s established operating system rather than requiring a new standalone CHPP, rail-loading and export chain.

What actually changes on the ground?

BMA estimates the continuation will extract approximately 55Mt of ROM metallurgical coal over the project period. The approved project continues the same broad open-cut mining approach already used at Saraji, including vegetation clearing, topsoil removal, drilling and blasting, overburden and interburden removal, coal extraction, spoil placement and progressive rehabilitation.

Mining is expected to continue using dragline, truck and shovel/excavator methods. Coal will continue to be processed and loaded through existing Saraji infrastructure.

Brownfield mining system Existing Saraji operation → Grevillea continuation → existing processing and rail
01 Mine planning Sequencing and pit progression from the current Grevillea footprint into ML700021.
02 Drill & blast Continuation of overburden and interburden drilling and blasting.
03 Overburden removal Dragline, truck and shovel/excavator methods expose the coal measures.
04 ROM coal Approximately 55Mt ROM metallurgical coal estimated across the continuation area.
05 Existing CHPP Processing remains within Saraji’s established mine infrastructure area.
06 Rail + export chain Existing train load-out and rail infrastructure remain part of the operating system.
Production clarification: the approximately 55Mt figure is an estimated ROM quantity associated with the continuation project. BMA’s preliminary documentation explicitly states the project will not increase Saraji’s annual product tonnage output. It is intended to sustain the mine’s existing production profile by allowing Grevillea to continue beyond the current lease boundary.

The real brownfield advantage: most of Saraji’s operating system already exists

Saraji already operates as a large integrated mine complex with coal processing, rail loading, stockpiles, tailings, water systems, electrical infrastructure, roads, workshops, offices and maintenance facilities.

That is why Grevillea should be read as a sustaining-life project rather than a conventional greenfield build.

Existing operating platform Grevillea extends the life of demand across an established mine system
Processing CHPP + stockpiles Existing coal handling, preparation and stockpile infrastructure remains in service.
Logistics Train load-out + rail The project continues to use the existing Saraji product movement and rail interface.
Water Dams, drains + pipelines Water-management infrastructure remains a core operating and compliance workstream.
Operations Roads, power + workshops Existing mine access, electrical, workshop, laydown and support infrastructure continues to underpin mining.

Within ML700021, BMA’s planning identifies continued or relocated supporting infrastructure including haul roads, pit ramps and benches, spoil areas, flood-protection levees, dams, drains and pipelines, an earth-moving-equipment build pad, electrical lines and substations.

Do not confuse Grevillea with the separate Saraji East project

Grevillea Pit Continuation Brownfield open-cut continuity

The newly approved Grevillea project extends the existing open-cut pit into ML700021, uses established Saraji infrastructure, adds about 55Mt ROM and is designed to sustain existing output through to around FY2055.

Separate project Saraji East underground development

Saraji East is a different underground mine proposal with its own development concept and approvals history. BBI has covered that project separately. The Grevillea approval should not be interpreted as approval or commitment for Saraji East.

Read BBI’s separate background coverage: Saraji East Project — BMA, Bowen Basin .

The contractor signal

The opportunity is recurring work — not one giant EPC package

The biggest commercial implication is duration.

Grevillea supports an operating mine that will continue consuming engineering, maintenance, equipment support, civil, environmental, water and rehabilitation services as the mining sequence advances.

Individual packages will depend on BMA’s operating and procurement strategy, but the approval strengthens the long-term base case for activity around Saraji.

BBI contractor continuity graphic for Saraji Grevillea showing mine planning dragline maintenance fleet support roads power water CHPP reliability and rehabilitation through 2055
BBI contractor watch artwork — Grevillea’s commercial significance is the duration of sustaining work around an established mine.

Where does long-duration contractor demand sit?

Mining front Pit progression creates recurring civil and earthworks requirements

Haul roads, ramps, benches, access, drainage, spoil placement, levees, pads and supporting earthworks remain essential as Grevillea advances into ML700021.

Existing production system The CHPP and materials-handling system still have to perform for decades

Mechanical reliability, structural maintenance, conveyors, pumps, piping, electrical systems, instrumentation, shutdown support and plant upgrades remain relevant to long-term production continuity.

Compliance + operations Water, power and rehabilitation become long-duration workstreams

Dams, drains, pipelines, groundwater monitoring, flood protection, electrical distribution, progressive rehabilitation and closure planning remain embedded in the mine’s operating requirements.

Core production Dragline, truck-and-shovel and mobile-equipment support remain central

Drill and blast, heavy-equipment maintenance, tyres, fuel, field service, components, workshops, planning, surveying and operational support are the recurring capabilities behind the approved continuation.

BBI Supply-Chain Lens Five capability areas where a long mine-life can matter more than a single project capex number
Heavy equipmentDragline, truck, shovel, excavator and field-service support.
Plant reliabilityCHPP, materials handling, mechanical, structural and electrical sustaining work.
Mine civilRoads, ramps, pads, drainage, levees and earthworks as the pit advances.
Water + environmentMonitoring, pumps, pipelines, groundwater, surface water and compliance delivery.
RehabilitationProgressive landform, closure planning, monitoring and rehabilitation execution.

Long-term workstreams worth tracking

01
Mine planning & schedulingPit sequencing, geotechnical inputs, design and operational planning.
02
Drill & blastOverburden, interburden and production-support drilling and blasting.
03
Dragline supportMaintenance, component work, shutdowns, electrical and mechanical support.
04
Mobile plantTruck, shovel, excavator, dozer, grader and support-equipment maintenance.
05
Haul roads & civilRoads, ramps, pads, drainage, levees and mine-area earthworks.
06
CHPP reliabilityMechanical, structural, piping, electrical and process-plant sustaining work.
07
Materials handlingConveyors, stockpiles, transfer systems and train-loading interfaces.
08
Water managementDams, drains, pipelines, pumps, monitoring and mine-water compliance.
09
Power distributionOverhead lines, substations, relocations and electrical maintenance.
10
Geotechnical & surveyPit walls, monitoring, surveying and mine-design verification.
11
Environmental monitoringEcology, water, groundwater, reporting and approval-condition compliance.
12
RehabilitationProgressive rehabilitation, landform work, monitoring and closure planning.
Procurement status: these are capability areas to monitor, not a list of live tenders. The approval strengthens the long-term operating case for Saraji, but specific packages should only be treated as open when released by BMA or an authorised procurement channel.

The approval also sits inside a wider environmental and economic debate

The Commonwealth assessment focused on nationally significant environmental matters including listed threatened species and communities and water resources. Technical assessment material considered habitat for species including the greater glider, koala, southern squatter pigeon and ornamental snake, as well as surface water, groundwater and groundwater-dependent ecosystems.

Operational case BMA frames Grevillea as continuity for an established regional operation

BMA says Grevillea supports existing Saraji operations and enables production to proceed as planned. Its project documentation argues that using established rail, road, power, water, processing and support infrastructure avoids the wider infrastructure footprint associated with a new greenfield mine.

Environmental response Climate and conservation groups have challenged the long operating horizon

Greenpeace, the Climate Council and Central Queensland environmental advocates have criticised the approval, citing the additional coal extraction, long project life, climate impacts, habitat disturbance and water-resource concerns.

The approval decision does not remove that debate. For BBI’s Project Watch purpose, the key distinction is between the fact of approval, the operational work it enables, and the environmental conditions and obligations that remain attached to delivery.

BBI Saraji Grevillea approval watch graphic showing federal approval conditions, environmental monitoring, water management, rehabilitation and long term mine operations to 2055
BBI approval watch artwork — the focus now shifts from the primary Commonwealth assessment to execution, compliance and long-term mine continuity.
Approval → execution

The next useful signals will come from operating plans, sustaining works and compliance delivery

With the Commonwealth approval now secured, the market should watch how BMA sequences mining into ML700021, what supporting infrastructure is relocated or constructed and how water, rehabilitation and environmental obligations are implemented.

Those details are more commercially useful to contractors than treating the approval itself as a single capital project.

What is confirmed — and what should the market avoid assuming?

Confirmed / documented
  • Federal EPBC approval has been granted with conditions.
  • Project reference is EPBC 2023/09757.
  • The continuation area is approximately 220ha in ML700021.
  • The mining footprint extends east from the existing Grevillea Pit in ML1782.
  • Approximately 55Mt ROM metallurgical coal is estimated.
  • The project horizon extends to approximately FY2055.
  • The project is intended to sustain existing output, not increase annual product tonnage.
  • Existing Saraji CHPP, train load-out, stockpiles, water and support infrastructure will continue to be used.
  • Dragline and truck/shovel-excavator mining methods continue.
  • Progressive rehabilitation forms part of the project.
Next market signals
  • Detailed mine-sequence timing into ML700021.
  • New or relocated haul roads and pit infrastructure.
  • Water-management works and monitoring requirements.
  • Electrical relocations and supporting substations.
  • Flood-protection and drainage works.
  • Earth-moving-equipment build-pad relocation.
  • Equipment maintenance and shutdown packages.
  • CHPP and materials-handling sustaining projects.
  • Environmental offset and monitoring delivery.
  • Progressive rehabilitation works.
  • Specific tender and supplier releases from BMA.
BBI Project Watch Assessment

2055 matters because duration — not new capacity — is the commercial story

Grevillea is not a new mine and it is not designed to lift Saraji’s annual product output.

That actually makes the approval more relevant to a different part of the Queensland contractor market.

A greenfield development can create a concentrated construction cycle. A continuation project works differently: it protects an operating base that can keep maintenance teams, field-service providers, engineering firms, drill-and-blast suppliers, equipment specialists, water contractors, civil crews and rehabilitation providers relevant year after year.

BMA’s own documentation points to the scale of that continuity: about 55Mt ROM from the continuation area, an approximately 220ha footprint and an operating horizon to FY2055 while continuing to use Saraji’s established CHPP, rail, water, power and maintenance systems.

The federal decision therefore does more than approve another pit boundary. It removes a major approval uncertainty from the long-term mine sequence at one of the Bowen Basin’s most established metallurgical-coal operations.

For suppliers, the question is not “when does the new mine get built?” It is “which sustaining scopes will BMA need to keep Saraji productive, compliant and reliable for the next three decades?”

What contractors and suppliers should watch next

Grevillea mine-sequence updates
ML700021 mobilisation
Haul-road works
Pit ramp development
Water-management packages
Flood-protection works
Power relocations
Dragline maintenance
Heavy fleet support
CHPP sustaining capital
Environmental monitoring
Progressive rehabilitation
Industry question For contractors, which is more valuable over time: one large construction cycle, or decades of recurring sustaining work around an established mine?

Grevillea is a useful example of why Project Watch is not only about headline construction capex — mine-life continuity can be just as important for the regional supply chain.

BBI Industry Directory

Find firms positioned to support Bowen Basin mine operations

Explore mining-service, engineering, civil, maintenance and industrial capability across the Isaac Region and wider Bowen Basin.

Sources

  1. Industry Queensland — Green light for Saraji mine’s Grevillea pit extension
  2. BHP — Regulatory information: Saraji Mine Grevillea Pit Continuation Project EPBC 2023/09757
  3. Independent Expert Scientific Committee — Saraji Mine Grevillea Pit Continuation Project advice
  4. BHP — Saraji mine
  5. Climate Council — response to the Grevillea approval
  6. Environmental Advocacy in Central Queensland — Grevillea submission / criticism
Disclaimer: Bowen Basin Index provides project, procurement, construction and industry information based on publicly available information. The Saraji Mine Grevillea Pit Continuation Project is an extension of existing open-cut mining operations at Saraji, not a new standalone mine. Public reporting on 3 September 2026 states that the Commonwealth has approved the project under the Environment Protection and Biodiversity Conservation Act 1999 with conditions. The project is identified as EPBC 2023/09757. BMA’s preliminary documentation identifies an approximately 220-hectare project/disturbance area within ML700021, east of the existing Grevillea Pit in ML1782, and estimates approximately 55 million tonnes of run-of-mine metallurgical coal over the project period. The documentation states that the project is intended to sustain existing Saraji operations and will not increase the mine’s annual product tonnage output. References to FY2055 describe the project planning horizon in BMA’s approval material and should not be interpreted as a guarantee that mining will continue without interruption to that date. Actual production remains subject to mine planning, geology, market conditions, commercial decisions, regulatory compliance, safety performance and other operating factors. References to approximately 16Mtpa describe the ROM scale stated in BMA’s project documentation and are not a forecast of annual saleable coal attributable to Grevillea. Existing and proposed supporting infrastructure discussed in this article includes the CHPP, train load-out, rail, stockpiles, tailings, roads, power, water-management systems, workshops, mine roads, pit infrastructure, levees, dams, drains, pipelines, earth-moving-equipment facilities and electrical infrastructure identified in BMA’s documentation. Mention of these infrastructure and service areas does not mean a specific contract, tender or procurement package is presently open. The Commonwealth assessment considered matters including listed threatened species and ecological communities and water resources. Environmental groups have publicly criticised the approval and the long operating horizon, while BMA has emphasised continuity of an established operation and regional economic contribution. BBI presents those positions as part of the public debate and does not imply that either position represents the approval conditions themselves. Saraji East is a separate underground project and is not the same project as the Grevillea Pit Continuation. BBI editorial artworks used with this article are illustrative and should not be relied upon as official mining-lease maps, mine plans, engineering drawings, environmental-condition maps, procurement schedules or confirmation of any specific contractor opportunity.