Project Watch Energy Gas Infrastructure Surat Basin
Investment decision — August 2026

Surat Gas Project Central is moving into its next development phase, with Shell and PetroChina backing Arrow Energy’s 143-well expansion south of Chinchilla and first gas targeted for 2028.

Shell announced the investment decision on 5 August 2026, confirming the next phase of Arrow Energy’s Surat Gas Project Central in Queensland’s Western Downs.

The development comprises 143 backfill gas wells and is expected to produce around 84 terajoules of natural gas per day at peak.

The physical delivery scale is clearly defined: 143 wells, a 2028 first-gas target and another sanctioned development phase moving into the wider Surat Basin construction pipeline.

Surat Gas Project Central Project Watch showing Arrow Energy's 143-well expansion backed by Shell and PetroChina with first gas targeted for 2028
BBI Project Watch — Arrow Energy’s 143-well Surat Gas Project Central expansion.
Project Pulse Investment Approved
143 Backfill Wells
84TJ/d Peak Gas Output
2028 First Gas Target
50/50 Shell / PetroChina
27 Years SGP Gas Agreement
Fresh development — 5 August 2026 Shell has approved investment in the next phase of Arrow Energy’s Surat Gas Project, advancing a 143-well development expected to produce around 84TJ/day at peak and deliver first gas in 2028.
Project-value note: Shell and Arrow Energy have not publicly disclosed an investment value for Surat Gas Project Central. Accordingly, no project dollar value is attributed to the development in this article.
Project Snapshot
Project Surat Gas Project Central
Operator Arrow Energy
Shareholders Shell 50% / PetroChina 50%
Location South of Chinchilla, Western Downs
Development 143 backfill gas wells
Peak Production Approximately 84TJ/day
Stage One Scheduled from second half of 2026
First Gas Targeted for 2028
Markets Domestic gas and LNG customers
Export Connection QCLNG, Curtis Island near Gladstone

Surat Gas Project Central moves forward south of Chinchilla

Arrow Energy describes Surat Gas Project Central as its third major development area within the broader Surat Gas Project.

The development is located south of Chinchilla in Queensland’s Western Downs, with planning and early works progressing alongside local landholders in the Kogan region.

Arrow says Stage One is scheduled to begin during the second half of 2026.

The project is expected to create longer-term benefits across communities including Chinchilla, Kogan, Brigalow and Hopeland, placing the development firmly within one of Queensland’s most established gas-service regions.

Illustrative Surat Gas Project Central gas well pad with drilling rig representing Arrow Energy's 143-well Western Downs development
Illustrative BBI image representing gas-well drilling and well-pad construction.
Well Development

143 wells turn the announcement into a physical construction program

Gas developments require repeated construction activity across individual well locations rather than a single central project site.

Typical field development can involve pad preparation, drilling, completions, wellhead facilities, access, gathering connections, rehabilitation and ongoing well servicing.

143 backfill wells define the physical scale of the expansion

Shell’s investment announcement identifies 143 backfill wells within Surat Gas Project Central.

The 143-well scope provides a clear physical measure of the development even though no project investment value has been publicly disclosed.

Each gas well ultimately needs to connect into the wider production system, creating interfaces across drilling, well facilities, access infrastructure, gas gathering, water handling, electrical and instrumentation systems, field logistics and ongoing maintenance.

Physical Development What is confirmed for SGP Central
143 Backfill production wells
84TJ/d Expected peak production
H2 2026 Stage One scheduled to begin
2028 First gas target

The Central expansion sits inside a much larger 27-year gas project

Surat Gas Project Central is one component of Arrow Energy’s much larger multi-phase Surat Gas Project.

Arrow says the overall project extends across Queensland’s Surat Basin, with licences stretching from Wandoan to south-west of Toowoomba and development already occurring around Miles, Dalby and south of Chinchilla.

When fully operational, the broader Surat Gas Project is intended to deliver up to 700TJ of natural gas per day.

The development is underpinned by a long-term gas sales arrangement that allows Arrow’s gas to utilise existing Shell QGC infrastructure.

That use of established infrastructure is strategically important because it allows additional gas fields to be developed without duplicating every major processing and transmission asset.

A gas well is only the beginning of the infrastructure chain

The contractor scope around Surat Gas Project Central extends well beyond drilling rigs.

Producing gas from a dispersed field requires infrastructure that connects individual wells into gathering and processing systems and manages the water produced alongside coal seam gas.

01
Well Pads Site preparation, drilling and well facilities.
02
Gathering Gas and water gathering connections.
03
Field Infrastructure Roads, utilities, controls and supporting facilities.
04
Processing Gas enters the wider Arrow / Shell QGC system.
05
Market Domestic customers and QCLNG export supply.
Gathering Infrastructure

Pipeline and gathering work links dispersed wells into the gas network

Arrow’s broader Surat Gas Project uses gas and water gathering networks to connect production wells with field and processing infrastructure.

These types of works can involve trenching, pipe installation, crossings, access roads, valves, testing, rehabilitation and associated control infrastructure.

Illustrative Surat Gas Project Central gathering pipeline construction with excavator trenching and field crews in Queensland's Western Downs
Illustrative BBI image representing gas gathering and pipeline construction.

Surat Gas Project Central could support a broad regional contractor workstream

The investment decision increases certainty around another defined phase of Arrow’s Surat Basin development.

That matters for contractors because a 143-well field program can require repeated mobilisation across drilling, construction, gathering, road access, logistics and ongoing field services.

The following capability areas are relevant to gas-field development and the broader infrastructure types Arrow uses across the Surat Gas Project.

Opportunities for Industry Capability areas to monitor as SGP Central progresses
Well-pad preparation
Gas-well drilling
Well completions
Well servicing
Civil earthworks
Access-road construction
Road maintenance
Gas gathering lines
Water gathering lines
Pipeline trenching
HDPE pipeline installation
Steel pipeline works
Pipeline testing
Mechanical installation
Electrical works
Instrumentation
SCADA & controls
Telecommunications
Water-management infrastructure
Environmental services
Surveying
Land access support
Plant & equipment hire
Crane & lifting
Heavy transport
Freight & logistics
Fuel supply
Mobile camps
Workforce accommodation
Waste management
HSE support
Inspection & testing
Operations support
Field maintenance
Well intervention
Site rehabilitation
Procurement note: these are relevant gas-development capability areas, not a statement that all of these packages have been released specifically for Surat Gas Project Central. Contractors should verify current procurement status through Arrow Energy, its nominated major contractors or authorised procurement channels.
Illustrative Surat Gas Project Central gas processing and field compression infrastructure supporting Arrow Energy production in the Surat Basin
Illustrative BBI image representing gas processing and field infrastructure.
Gas Infrastructure

The development connects into an established regional gas system

One of the defining features of Arrow’s Surat Gas Project is its ability to use existing third-party infrastructure under its long-term arrangements with Shell QGC.

This allows new production areas to feed into a wider network spanning field infrastructure, processing, domestic gas supply and LNG export facilities.

Gas will serve both domestic customers and QCLNG at Curtis Island

The commercial destination of the gas gives Surat Gas Project Central relevance well beyond the Western Downs.

Shell says production from the development will support domestic gas customers as well as international LNG customers through the Shell QGC-operated Queensland Curtis LNG facility on Curtis Island near Gladstone.

That means the project effectively links gas-field development south of Chinchilla with the broader Queensland industrial and LNG supply chain.

Arrow’s arrangement with Shell QGC is based on a 27-year gas sales agreement announced in 2017.

The connection links regional drilling and gas-field construction with downstream industrial infrastructure and export activity around Gladstone.

Related coverage is available through Gas Infrastructure , Energy and Supply Chain .

The investment decision gives SGP Central a defined delivery pathway

Shell’s announcement confirms a sanctioned development phase with a specific operator, a defined 143-well physical scope, an expected production rate and a 2028 first-gas target.

The project has therefore moved beyond concept-stage planning into a defined implementation pathway.

Near-term delivery will depend on how Stage One progresses through landholder engagement, early works, drilling, gathering infrastructure and eventual commissioning before first gas.

Contractor & Supplier Pathway Arrow Energy maintains an active supplier registration process

Arrow Energy operates a dedicated supplier and contractor portal covering contracting opportunities, HSE requirements, procurement information, site training and supplier systems.

Arrow’s contracting-opportunities page currently states that it is seeking expressions of interest for work packages and directs businesses to its Supplier Registration Form and the Industry Capability Network Gateway.

Arrow also notes that many smaller-supplier opportunities can flow through its major contractors rather than directly through Arrow.

Important: Arrow’s supplier portal covers its broader operations and current contracting activity. Its presence does not confirm that every current expression of interest is specifically associated with the 143-well Surat Gas Project Central development. Suppliers should review individual opportunity descriptions before responding.

Chinchilla and the Western Downs remain central to Queensland’s gas-contractor market

The location of the new development is particularly relevant for businesses already operating across Chinchilla, Kogan, Dalby, Miles, Brigalow and the wider Surat Basin.

The region has an established contractor base across drilling, pipelines, civil construction, equipment hire, transport, electrical services, mechanical maintenance and gas-field operations.

That existing supply chain should be well positioned to follow the Central expansion as the project advances toward first gas.

Regional capability can also be explored through the Darling Downs & Surat Basin Industrial Services Directory or browse businesses listed specifically across the Darling Downs and Surat Basin .

Project Delivery Outlook

The 143-well program establishes a multi-year Western Downs delivery pipeline

Surat Gas Project Central now has a defined operator, committed shareholders, 143 backfill wells, an expected peak production rate of around 84TJ/day and a 2028 first-gas target.

That level of physical definition moves the project into a clearer implementation and procurement phase.

Field development of this type can create work across well pads, drilling, completions, civil works, roads, gathering infrastructure, water management, electrical and instrumentation, logistics and long-term field maintenance.

Near-term indicators include Stage One early works, landholder access, well-pad construction, drilling mobilisation, gathering infrastructure, supplier EOIs and progression toward commissioning and first gas in 2028.

What businesses should watch next

Stage One early works
Landholder access and site preparation
Well-pad construction
Drilling-rig mobilisation
Well-completion packages
Civil-construction packages
Access-road works
Gas-gathering construction
Water-gathering infrastructure
Electrical and instrumentation work
SCADA and communications
Equipment-hire requirements
Heavy transport and freight
Workforce accommodation
Arrow supplier EOIs
Major-contractor subcontract opportunities
Commissioning activity
Progress toward 2028 first gas
BBI Industry Directory

Find industrial capability across the Surat Basin

Search engineering firms, civil contractors, equipment providers, logistics businesses, maintenance specialists and regional suppliers supporting Queensland’s energy and resource projects.

With 143 wells now backed for development, which part of Surat Gas Project Central is likely to create the strongest regional contractor demand — drilling, gathering pipelines, civil works, field services or long-term maintenance?

Sources

  1. Shell Australia — Shell invests in next phase of Arrow Energy’s Surat Gas Project, 5 August 2026
  2. Arrow Energy — Surat Gas Project Central
  3. Arrow Energy — Surat Gas Project overview
  4. Arrow Energy — Surat Gas Project North expansion and broader SGP infrastructure context
  5. Arrow Energy — Supplier and contractor portal
  6. Arrow Energy — Contracting opportunities and supplier registration
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available sources available at the date of publication. Shell and Arrow Energy have not disclosed a project investment value for Surat Gas Project Central in the public material reviewed for this article. No dollar value is therefore attributed to the development. References to potential contractor, subcontractor, supplier, employment or service opportunities are general observations based on the announced 143-well development, the broader Surat Gas Project infrastructure model and typical gas-field delivery requirements. Except where an official Arrow Energy registration or expression-of-interest pathway is specifically linked, the capability areas identified in this article should not be interpreted as currently available separate tenders, contracts or subcontract packages for Surat Gas Project Central. Businesses should verify current procurement opportunities, supplier-registration requirements, project schedules and scopes directly with Arrow Energy, Shell, relevant major contractors or authorised procurement channels. Production forecasts, first-gas timing, development scope and project sequencing may change as implementation progresses. Illustrative editorial images used in this article should not be interpreted as official photographs documenting current Surat Gas Project Central construction activity.