Final investment decision • 20 August 2026
Mount Isa energy infrastructure

$259 million.
Construction starts late this year — and the mine customer is already locked in.

APA Group has made a final investment decision on the Sybella Creek Solar Farm and Battery Energy Storage System in Mount Isa, committing $259 million to a new renewable-energy project backed by long-term mining demand.

The project will combine a 72MW solar farm with a 52MW / 104MWh BESS and is underpinned by an Energy Supply Agreement with Evolution Mining’s Ernest Henry operation through to mid-2046.

With construction targeted to begin in late 2026, the story now moves from project development into physical delivery.

APA 259 million dollar Sybella Creek Solar Farm and battery energy storage project in Mount Isa backed by Ernest Henry Mine
BBI Project Watch — APA has reached FID on the $259M Sybella Creek solar and battery project.
Project Wire
$259M committed 72MW solar 52MW / 104MWh BESS FID achieved Late-2026 construction Mid-2028 completion Ernest Henry agreement to mid-2046 $259M committed 72MW solar 52MW / 104MWh BESS FID achieved Late-2026 construction Mid-2028 completion Ernest Henry agreement to mid-2046
Project Pulse Mining demand, committed capital and a clear construction window now line up.
$259M APA Investment
72MW Solar Farm
104MWh Battery Storage
2046 Energy Agreement
Why this project matters This is no longer a speculative renewable proposal. APA has approved the capital, the industrial customer is secured and construction is scheduled to begin within months.

APA says it will construct, own and operate the Sybella Creek renewable-energy assets.

The $259 million investment will be funded from APA’s existing balance-sheet capacity and forms part of the company’s broader organic growth pipeline.

Construction is anticipated to start in late 2026, with completion planned for mid-2028.

Contractor status: APA’s FID announcement does not publicly identify a principal EPC or construction contractor for Sybella Creek. That makes contractor appointments, procurement notices and early works the next major industry milestones to monitor.

The project combines two new assets with APA’s existing Mount Isa generation base

New generation 72MW Solar Utility-scale solar generation developed locally within the Mount Isa energy system.
New storage 52MW / 104MWh BESS Battery storage designed to strengthen reliability and resilience while shifting renewable energy across the operating cycle.
Existing firming Diamantina APA’s existing gas-powered facility will provide firming capacity and complementary energy supply.

The result is a hybrid supply model rather than a stand-alone solar development.

APA says the combination of solar generation, battery storage and gas-powered firming is intended to deliver lower-emissions electricity with greater reliability for Ernest Henry.

Why the Sybella Creek Mount Isa solar and BESS project matters for mining energy and construction
BBI editorial graphic summarising the FID, mine-backed demand and project timing.
FID changes the story

The project has moved from development into execution

FID means APA has approved the investment and committed to progressing the project.

For contractors, that shifts attention toward delivery structure, procurement, mobilisation and construction packaging rather than whether the development will reach an investment decision.

Ernest Henry gives the project a long-term industrial customer

The project is underpinned by an Energy Supply Agreement with Ernest Henry Mining Pty Ltd, the wholly owned Evolution Mining subsidiary that operates Ernest Henry.

The agreement runs until mid-2046.

That long-duration supply position is one of the strongest commercial features of the project because the new generation and storage capacity is being developed against identifiable industrial demand.

APA says the arrangement will also support the long-term operation and improved efficiency of its existing Diamantina Power Facility.

Why the mining connection matters: Sybella Creek is not being developed as renewable capacity without a named end user. Ernest Henry’s demand provides a direct industrial-use case and long-term contracted foundation for the investment.

Solar supplies energy. Batteries shift it. Gas provides firming.

The operating model also explains why the project is particularly relevant in North West Queensland.

The North West Power System serves major resource operations in a remote electricity network where reliability is critical.

APA says the BESS is expected to strengthen network reliability and resilience for Ernest Henry and more broadly for mining customers and the local community across the system.

The project therefore combines new renewable capacity with an existing dispatchable generation asset rather than attempting to replace firming capability altogether.

The construction clock is already running

FID 20 August 2026
Construction Late 2026
Completion Mid-2028 target
Energy Supply Agreement to mid-2046

That schedule gives the contractor market a relatively narrow pre-construction window.

If major physical works are to begin in late 2026, engineering, procurement, equipment ordering, enabling works and contractor mobilisation become increasingly important over the coming months.

Where could the physical work land?

APA has not yet publicly broken the project into detailed contract packages in its FID announcement.

Based on the confirmed solar and BESS scope, however, several construction disciplines are directly relevant to the delivery phase.

01
Civil works Site formation, access roads, drainage, pads and general earthworks.
02
Solar piling Driven foundations and support systems for solar-array installation.
03
Solar installation Module, tracker or mounting-system assembly and field installation.
04
Battery compound Foundations, hardstands, equipment placement and supporting infrastructure.
05
Substations Transformers, switchgear, protection systems and connection infrastructure.
06
HV electrical High-voltage connections, switchyards, earthing and associated electrical works.
07
Cabling DC, AC and communications cabling, trenching and cable-management systems.
08
Controls & SCADA Control systems, communications, protection and plant integration.
09
Fencing & security Perimeter fencing, access control and security infrastructure.
10
Heavy haulage & craneage Battery units, transformers, major electrical equipment and lifting.
11
Testing & commissioning Electrical testing, energisation, control integration and performance verification.
12
Operations & maintenance Long-term inspection, servicing, electrical maintenance and asset support.
Contractor exposure

The workstream story is strongest after FID

Civil, solar, battery and HV construction are no longer attached only to an early development concept.

They sit behind a capital commitment with a stated construction start and completion window.

Actual package boundaries and contractor appointments still need to be confirmed by APA.

Potential contractor exposure for Sybella Creek solar and BESS including civil works piling solar installation battery compounds substations HV cabling controls fencing heavy haulage craneage and commissioning
Potential workstreams associated with the announced solar and BESS scope. Individual packages are not yet confirmed.

What is confirmed — and what should contractors still watch?

Confirmed
  • APA has reached final investment decision.
  • APA will invest approximately $259M.
  • 72MW Sybella Creek Solar Farm.
  • 52MW / 104MWh BESS.
  • Construction targeted for late 2026.
  • Completion planned for mid-2028.
  • Ernest Henry ESA runs to mid-2046.
  • APA will construct, own and operate the assets.
Watch next
  • Principal EPC or construction contractor.
  • Early civil contractor appointments.
  • Solar module and mounting packages.
  • BESS technology supplier.
  • Transformer and substation procurement.
  • HV connection works.
  • Heavy-haul and crane requirements.
  • Local supplier and subcontract opportunities.
BBI Project Watch Assessment

This project has nearly every ingredient contractors look for

$259 million of committed investment.

A final investment decision has already been made.

The project has a named mining customer, a long-term energy agreement, clear solar and storage capacity and a construction start expected within months.

That makes Sybella Creek considerably more advanced than renewable projects that are still seeking approvals, customers or investment decisions.

The next value for BBI readers comes from identifying who actually builds it.

APA has not yet publicly named the principal delivery contractor in the FID material reviewed by BBI, so the project now moves onto the procurement watchlist for civil works, solar installation, BESS construction, substations, HV systems, heavy transport and commissioning.

The long-term Ernest Henry agreement also means the story extends beyond construction. Once operating, the project will create an ongoing asset base requiring maintenance, electrical support, inspection and lifecycle services through a multi-decade energy-supply period.

What industry should watch next

Principal contractor appointment
EPC structure
Early earthworks
Solar piling packages
Module supply
Mounting / tracker system
BESS technology supplier
Battery-compound civils
Transformer procurement
Substation package
HV connection works
Electrical cabling
Controls and SCADA
Heavy haulage
Craneage
Testing and commissioning
Local supplier engagement
Long-term O&M contracts
BBI Industry Directory

Find North West Queensland firms positioned for mining and energy construction

Search engineering, civil, electrical, equipment, logistics and industrial-service firms supporting Mount Isa and the North West Minerals Province.

With FID complete and construction targeted for late 2026, which package will be the first major contractor signal — civil works, solar installation, BESS delivery or the high-voltage connection?

Sources

  1. APA Group — APA to construct, own and operate the Sybella Creek Solar Farm and Battery Energy Storage System in Mount Isa, 20 August 2026
  2. APA Group — FY26 results and growth pipeline update, 20 August 2026
  3. Evolution Mining — Ernest Henry operation and corporate information
  4. Utility Magazine — APA to build Sybella Creek solar farm and battery in Mount Isa, 20 August 2026
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information current at the date of publication. APA Group announced on 20 August 2026 that it had reached final investment decision to construct, own and operate the Sybella Creek Solar Farm and Battery Energy Storage System in Mount Isa, Queensland. APA has stated that it will invest approximately $259 million in the project. The confirmed announced scope comprises a 72MW solar farm and a 52MW / 104MWh battery energy storage system. The $259 million figure refers to APA’s overall project investment and should not be interpreted as the value of any individual civil, electrical, solar, battery, substation, heavy-haul or commissioning contract. APA’s investment is underpinned by an Energy Supply Agreement with Ernest Henry Mining Pty Ltd, a wholly owned subsidiary of Evolution Mining, running until mid-2046. APA has stated that its existing Diamantina Power Facility will provide firming capacity and energy supply alongside the new renewable-energy assets. Construction is anticipated to commence in late 2026 and project completion is planned for mid-2028. These dates are project targets and may change as engineering, procurement, construction and commissioning progress. Bowen Basin Index has not identified a publicly named principal EPC or construction contractor for Sybella Creek in APA’s final investment decision announcement reviewed for this article. References to civil works, piling, solar installation, battery compounds, substations, high-voltage electrical works, cabling, controls, fencing, heavy haulage, craneage, testing, commissioning and operations and maintenance describe potential capability areas associated with delivering and supporting a project of the announced type. Bowen Basin Index is not stating that each listed workstream has been released as a current tender, subcontract package or supplier opportunity. Actual package structure, procurement timing, contractor appointments, technology suppliers, prequalification requirements and local-content opportunities should be confirmed directly with APA Group or its subsequently appointed delivery contractors. BBI editorial images used in this article are illustrative graphics unless specifically identified otherwise. Images depicting solar arrays, BESS compounds, mines, transmission infrastructure or regional connections should not be interpreted as verified current Sybella Creek site photography, final engineering design, official electrical connection diagrams or approved transport routes unless separately identified.
Project information reviewed against APA Group’s 20 August 2026 FID announcement and current supporting project information — 23 August 2026.