MacIntyre Wind Farm now targets mid-2027 commercial operation as commissioning delays reshape offtake deals
MacIntyre Wind Farm is now a large operating asset that is still working through final commissioning. ACCIONA says more than 670 MW of the 923 MW project has been energised, both substations have been handed to the Operations team, and turbine commissioning, maintenance and reliability work are continuing. The company now expects commercial operation in mid-2027.
That delay has moved beyond the construction schedule and into the project's commercial arrangements. Fresh reporting based on the 2025–26 annual reports of Queensland government-owned CleanCo and Stanwell says CleanCo amended its MacIntyre offtake agreement and Stanwell is discussing revised long-term arrangements. For BBI readers, the important shift is that MacIntyre is no longer mainly a bulk-build story: the live market signal is commissioning, reliability, operations support and the commercial close-out of a delayed 923 MW wind project.

Commercial operation has moved to mid-2027 while customer agreements are being reset
The newest material development is the combination of a later commercial-operation target and changes to long-term offtake arrangements. RenewEconomy reported on 3 October that ACCIONA expects MacIntyre to reach commercial operation in mid-2027 and that more than 670 MW of the project's 923 MW capacity has been energised, about 73 per cent of the project.
The same report, citing the 2025–26 annual reports of CleanCo and Stanwell, says CleanCo amended its MacIntyre agreement to increase the volume purchased, extend the agreement term and resolve commercial matters associated with delayed delivery. Stanwell's accounts are reported as saying it is engaging with the developer regarding revised long-term offtake arrangements.
That is a stronger Project Watch trigger than a routine commissioning update because it links the delayed delivery program to the commercial structure around the project. ACCIONA says customer agreements are commercial in confidence, so BBI is not inferring pricing, compensation, damages or any other undisclosed contractual term.
MacIntyre is a 923 MW wind system spread across a large Southern Queensland footprint

ACCIONA lists MacIntyre at 923 MW with 162 wind turbines across a project area of about 32,000 hectares, roughly 50 kilometres south-west of Warwick and 10 kilometres south of Karara. The project sits across the Southern Downs and Goondiwindi local government areas and is one of Queensland's largest operating renewable-energy assets by nameplate scale.
The grid interface is also substantial. Powerlink's MacIntyre Wind Precinct Connection Project includes about 65 kilometres of new transmission line, 166 transmission towers and two switching stations. Powerlink says the connection works were completed by late 2023, with MacIntyre Substation North connected in August 2024 and Substation South connected in January 2025.
ACCIONA says the project had procured more than $980 million in services, labour and materials from Queensland by 31 March 2026, including $195 million with regional Queensland suppliers and $10.3 million with Indigenous businesses. Those figures describe historical project spend; they should not be read as a current tender pipeline.
The asset is energised at scale, but full commercial operation is still a commissioning outcome

ACCIONA's 22 September operations update says both substations have now been formally handed over to the Operations team. It also says Operations and Engineering & Construction personnel are working together while turbine commissioning continues, alongside planned maintenance, annual servicing and reliability improvements.
The distinction is important. A project can be producing significant electricity and operating parts of the asset while still not having reached full commercial operation. For MacIntyre, more than 670 MW is energised, but the remaining turbines, reliability work and project-level commissioning still sit on the path to the stated mid-2027 commercial-operation target.
Earlier commissioning updates also show why the close-out has taken time. ACCIONA said in November 2025 that detailed blade inspections followed the December 2024 blade failure and that repair works included replacement of the affected turbine and transport of new components. BBI treats those works as part of the commissioning history rather than evidence of a new construction package.
Industry relevance has shifted toward commissioning, reliability, maintenance and operations support

The current capability signal is different from the peak-construction phase. The fresh ACCIONA update points to turbine commissioning, planned maintenance, annual servicing, reliability improvements, environmental management and site improvement works as active areas of effort while the project transitions into long-term operations.
For Queensland suppliers, that makes specialist electrical and mechanical commissioning, controls and instrumentation support, high-voltage and grid-interface capability, turbine maintenance, reliability engineering, access and site services, environmental works, logistics and operational support more relevant areas to monitor than a broad new civil build program.
Those are capability areas, not confirmed open packages. BBI has not identified a new major tender, contractor award or procurement notice tied to the mid-2027 timing change. Businesses should treat formal notices from ACCIONA, its contractors and procurement channels as the authority on actual package availability.
The commissioning delay is now visible in the structure of long-term energy contracts
RenewEconomy says CleanCo's 2025–26 annual report records an amendment to the MacIntyre offtake agreement that increases the volume of energy purchased, extends the term and resolves commercial matters relating to delayed delivery. The publication also reports that CleanCo's contracted volume has increased from 400 MW to 490 MW.
CleanCo's public MacIntyre webpage still displays the older 400 MW offtake figure, so BBI is treating 490 MW as an annual-report disclosure reported by RenewEconomy rather than a figure independently reconciled across all CleanCo web material. That difference is worth watching because it shows public project pages can lag annual-report disclosures.
Stanwell's side remains less detailed publicly. RenewEconomy reports that Stanwell's accounts say it is engaging with the developer on revised long-term offtake arrangements, while Stanwell told the publication that those discussions are commercial in confidence. The commercial takeaway is therefore a confirmed renegotiation signal, not visibility on the undisclosed terms.
The next proof points are commissioning depth, reliability close-out and clearer contract visibility
The strongest next operational signal will be further increases in the amount of capacity cleared through commissioning, followed by evidence that remaining turbine and reliability work is closing out. A final declaration of commercial operation would mark the clearest project-stage change.
On the commercial side, BBI will watch future CleanCo and Stanwell disclosures for confirmation of the revised offtake structure, as well as any ACCIONA statements that materially change the mid-2027 target. Any formal procurement or contractor announcements associated with commissioning, maintenance or long-term operations would be separately reportable if they are material.
Until then, MacIntyre should be read as a project already generating at large scale but still working through the final technical and commercial steps required to become a fully commercially operating 923 MW wind farm.
- MacIntyre Wind Farm has a project capacity of 923 MW.
- The project comprises 162 wind turbines.
- ACCIONA says more than 670 MW has been energised.
- Both MacIntyre substations have been handed to the Operations team.
- Turbine commissioning, planned maintenance and reliability work are continuing.
- ACCIONA currently expects commercial operation in mid-2027.
- Powerlink's major connection works are complete.
- Fresh annual-report disclosures indicate CleanCo amended its offtake agreement and Stanwell is discussing revised long-term arrangements.
- Full commercial operation remains ahead and is currently targeted for mid-2027.
- The remaining commissioning and reliability close-out still has to be completed.
- Undisclosed commercial terms may continue to evolve because customer agreements are confidential.
- New procurement packages or contractor awards should not be assumed unless formally announced.
What industry should watch next
BBI: Bungaban Wind & Solar wins federal approvalBBI: Gawara Baya turbine package confirmedBBI: Wongalee Wind advances after EPBC approval
Sources and primary references
- ACCIONA — MacIntyre Wind Farm Operations Update, 22 September 2026
- ACCIONA — MacIntyre Wind Precinct project page
- Powerlink — MacIntyre Wind Precinct Connection Project
- RenewEconomy — MacIntyre offtake agreements revisited after delays, 3 October 2026
- CleanCo — MacIntyre Wind Farm public offtake page
- ACCIONA — Update on commissioning activities, 19 November 2025