Skip to main content

Bowen Basin Index

Project Watch Federal Referral Live Roma Phase 8B Stage 2 Coal Seam Gas Maranoa Region
Queensland gas-field development watch

Santos has advanced Roma Phase 8B Stage 2 into federal review, outlining up to 175 new CSG production wells.

Santos Ventures has referred the Roma Phase 8B Stage 2 Coal Seam Gas Development under the EPBC Act, putting a major new field-development program east of Roma into a formal Commonwealth decision process.

The proposal covers up to 175 production wells within ATP 2052, across a project area of about 8,894 hectares around 68 kilometres east of Roma and 10 kilometres east of Yuleba. Santos says eight appraisal wells drilled between 2022 and 2025 are intended to become part of the development.

Construction is proposed to commence from 2029 and progress over about five years. The current concept includes well leases, gas and water gathering, trunklines and pipelines, access roads, temporary water storage, temporary worker accommodation, power and communications infrastructure, with production tied into existing approved GLNG facilities.

Current stage: the EPBC referral is open for public comment and a controlled-action decision is still pending. This is not project approval, construction authorisation or confirmation that contract packages have been released.
BBI Project Watch graphic for Santos Roma Phase 8B Stage 2, highlighting up to 175 CSG wells and the federal EPBC referral in Queensland's Maranoa region.
BBI Project Watch — Roma Phase 8B Stage 2 is in the federal referral process. Editorial imagery is illustrative and does not depict an approved well layout or final construction plan.
Project PulseA proposed 175-well Roma gas-field expansion has moved into a live Commonwealth environmental decision process.
175Maximum Production Wells
8,894 haATP 2052 Project Area
2029+Proposed Construction Start
~5 yrsIndicative Build Program
Why this stage mattersThe referral exposes a defined physical scope and a potential 2029 field-development window. It gives contractors and suppliers a clearer project to monitor, but procurement remains a future signal rather than a confirmed market today.

Roma Phase 8B Stage 2 has entered the Commonwealth referral process

The EPBC Public Portal records Roma Phase 8B Stage 2 as referral 2026/10646, started on 8 September 2026 and currently at “Referral Decision — Open for Public Comment”. The immediate Commonwealth question is whether the proposed action is a controlled action requiring further assessment under the EPBC Act.

Santos Ventures Pty Ltd is the designated proponent and operator of ATP 2052. The referral describes progressive construction, operation, decommissioning and rehabilitation of up to 175 CSG production wells. That is a materially defined field-development proposal rather than a generic exploration program.

The proposal also builds on work already completed in the area. Santos says eight CSG appraisal wells and associated infrastructure were drilled and completed within ATP 2052 between 2022 and 2025, and the company intends those wells to form part of the proposed development.

BBI stage discipline: a referral creates a formal environmental decision point; it does not approve the project. Detailed engineering, final disturbance locations, procurement timing, contractor strategy and construction sequencing are not yet publicly confirmed.

The development combines well pads, gathering systems, roads and temporary support infrastructure

Illustrative aerial view of a distributed Queensland CSG field showing multiple well pads, access roads and gathering infrastructure representative of the published Roma Phase 8B Stage 2 scope.
BBI scope visual — illustrative only. The image is not an official ATP 2052 site plan, well layout or pipeline alignment.
Published project scope

A distributed field-development program across ATP 2052 east of Roma

The project area covers about 8,894 hectares in the Maranoa Regional Council area, approximately 68 kilometres east of Roma and 10 kilometres east of Yuleba. The referral says the preliminary disturbance footprint has been refined to about 609.5 hectares after environmental surveys and impact-avoidance work.

Individual well leases are expected to be about 1.25 hectares for a single well and up to about 3 hectares for multi-well leases. Water and gas gathering lines, trunklines and pipelines would generally use construction corridors about 20–35 metres wide, while roads and access tracks would typically use corridors about 10–15 metres wide.

Supporting works may include temporary water tanks, temporary camps, power and communications lines and other field infrastructure. The published concept therefore creates a broad delivery chain spanning drilling, civil, piping, electrical, communications, logistics and environmental capability if the project proceeds.

The referral does not propose a new major gas-compression or water-treatment facility inside the project area. Gas and produced water would instead be transferred through new and existing gathering infrastructure to existing approved facilities on adjacent Santos tenures, including connection toward the Roma field system.

Santos estimates about 246 megalitres of water could be needed to develop the project, with produced water preferred where practicable. The referral separately estimates about 2,790 megalitres of produced water over the development life, reinforcing that water management remains an important operational and environmental interface.

The federal decision is the next visible gate before any broader assessment pathway

Approval pathway

Referral now; assessment requirements and final project approvals remain ahead

The current EPBC stage is a referral decision, not an approval decision. The Commonwealth is considering whether the proposed action is likely to have a significant impact on protected matters and therefore requires assessment as a controlled action.

If a controlled-action decision is made, a further assessment pathway would be set before any final Commonwealth approval decision. Separate Queensland petroleum, environmental and land-access requirements also continue to apply to development activities.

The referral notes that field investigations and design work have already been used to avoid and minimise environmental impacts. That process is likely to continue as well locations, access, gathering routes and construction footprints are refined.

Illustrative engineering and survey fieldwork in Queensland gas country, representing the assessment and detailed-development work that may precede Roma Phase 8B Stage 2 construction.
BBI pathway visual — illustrative fieldwork only, not a confirmed Santos contractor, survey campaign or construction activity.
Confirmed now
  • EPBC referral 2026/10646 is live.
  • Up to 175 CSG production wells are proposed.
  • ATP 2052 covers about 8,894 ha east of Roma.
  • Eight appraisal wells already exist in the project area.
  • Construction is proposed from 2029 over about five years.
  • Gathering, access, temporary support, power and communications infrastructure form part of the concept.
Conditional / future
  • Controlled-action determination and any further EPBC assessment.
  • Final engineering, well locations and disturbance footprint.
  • Final field-development sequence and annual well rollout.
  • Contracting model, procurement packages and supplier registration.
  • Construction award timing and major contractor appointments.
  • Commissioning and production timing for individual development areas.

If approved, delivery would be a rolling field-development program rather than one single construction package

The practical delivery model for a distributed CSG development is different from a single plant build. Wells can be developed progressively while supporting roads, gathering systems, power and communications are extended across the field. The referral anticipates a multi-year program from 2029, consistent with staged development rather than one short construction campaign.

For industry, the physical scope points to capability areas including drilling and completions support, well-pad civil works, road and access construction, trenching and gathering installation, trunkline and pipeline works, temporary water storage and management, camp and logistics support, electrical and communications services, environmental fieldwork, rehabilitation and ongoing operations support.

Those are capability areas inferred from the published physical scope. BBI has not identified public evidence that Santos has released these as discrete tenders or awarded packages for Roma Phase 8B Stage 2.

Commercial trigger to watch: the strongest evidence that the project is moving from assessment into execution will be a defined development sequence, contracting strategy, supplier engagement, tender notices or contractor appointments tied specifically to ATP 2052.

The project sits inside an active Roma–GLNG upstream system with strong recent production

Illustrative Queensland gas-field logistics scene showing pipe handling, civil equipment, temporary facilities and regional delivery activity relevant to a future Roma Phase 8B field-development program.
BBI commercial visual — capability illustration only. It does not show confirmed Roma Phase 8B contracts, suppliers, tenders or awarded packages.
Commercial and strategic context

Existing infrastructure lowers the need for a standalone processing build inside ATP 2052

Santos operates the upstream side of GLNG, which links Queensland gas fields to a 420-kilometre transmission pipeline and the two-train LNG facility on Curtis Island. The company’s stated upstream strategy includes building gas supply around existing infrastructure and extracting more value from established systems.

That context is relevant to ATP 2052. The referral says Roma Phase 8B Stage 2 would connect into existing approved GLNG and gas-field infrastructure rather than construct a new large compression or treatment complex inside the project area.

Santos reported that the Roma field achieved record daily production of about 230 TJ/day gross in the second quarter of 2026, while GLNG upstream production averaged about 703 TJ/day gross. The new referral therefore sits alongside an operating gas system that is already materially active.

The commercial opportunity for regional contractors is consequently likely to be field-development and sustaining-capital oriented: distributed civil works, drilling support, gathering networks, electrical and communications extensions, logistics, environmental services and rehabilitation. The timing and packaging of any such work remain unconfirmed.

BBI is also tracking related Queensland gas and energy developments including the Surat Gas Project Central and the Central Queensland gas power tender.

What contractors and suppliers should watch next

The referral is important because it turns ATP 2052 into a defined project watchlist item with scale, location, physical scope and an indicative development window. It is still too early to treat the proposal as a live procurement program.

Commonwealth controlled-action decision
Any further EPBC assessment requirements
Final environmental and field-development approvals
Detailed well and gathering-system design
2029 development sequencing and drilling schedule
Road, pad and gathering construction strategy
Supplier registration and contractor engagement
Tender notices and work-package releases
Major contractor and service awards
Commissioning and tie-in milestones
BBI Industry DirectoryFind Queensland capability across gas, civil, mechanical, electrical, environmental and regional services.

Project Watch identifies the signals and capability areas to monitor. The BBI Directory helps project teams and contractors find businesses operating across regional Queensland.

Sources and primary references
  1. Australian Government EPBC Public Portal — Roma Phase 8B Stage 2 Coal Seam Gas Development referral summary
  2. Australian Government EPBC Public Portal — referral decision / public comment status
  3. Santos — 2026 Second Quarter Report
  4. Santos — Gladstone LNG / upstream gas and liquids
  5. Industry Queensland — Santos CSG development plans open for public comment
Disclaimer: Bowen Basin Index provides project, procurement, construction and industry information based on publicly available information reviewed to 27 September 2026. Roma Phase 8B Stage 2 is a proposed coal seam gas development in the Commonwealth referral process. The referral does not constitute project approval, final development sanction, construction authorisation, tender release or contractor award. The maximum 175-well scope, 8,894-hectare project area, approximately 609.5-hectare preliminary disturbance footprint, 2029 commencement signal and five-year development period are based on current public project information and remain subject to assessment, design refinement, approvals and commercial decisions. References to drilling, well pads, access roads, gathering systems, pipelines, water management, temporary camps, electrical and communications work, logistics, environmental services and rehabilitation describe capability areas associated with the published physical concept; they do not confirm that Santos has created, released, tendered or awarded individual packages. BBI editorial graphics are illustrative intelligence graphics only and are not official well maps, pipeline alignments, engineering drawings, schedules or procurement documents.