Project Watch Energy Contract Award Central Queensland
Updated August 2026

The Smoky Creek solar project near Biloela is moving deeper into delivery, with 720MWp of solar, 2.4GWh of battery storage, around 800 jobs and another major supply package now locked in.

DT Infrastructure has appointed TCL Solar to supply photovoltaic modules for Edify Energy’s Smoky Creek and Guthrie’s Gap Solar Power Stations near Biloela.

The award adds another confirmed package to an approximately A$1.1 billion dual-site EPC development combining utility-scale solar, battery storage and major high-voltage infrastructure.

The TCL Solar award adds to a broader delivery program in which one of Central Queensland’s largest renewable-energy developments is progressively moving into equipment supply, construction and installation packages.

Smoky Creek solar project near Biloela with DT Infrastructure delivering 720MWp solar and 2.4GWh battery storage
BBI Project Watch — Smoky Creek & Guthrie’s Gap, Central Queensland.
Project Pulse Major Project
720MWp Solar
2.4GWh Battery Storage
~$1.1B Contract Sum
~800 Project Jobs
2028 Target Completion
Latest package development TCL Solar has secured the 720MWp photovoltaic module-supply package from DT Infrastructure, with module installation expected to begin in early Q2 2027.
Project Snapshot
Project Smoky Creek & Guthrie’s Gap
Developer Edify Energy
EPC Contractor DT Infrastructure
Module Supplier TCL Solar
Location Near Biloela, Central Queensland
Solar 720MWp / 600MW connection
Battery 600MW / 2,400MWh BESS
Grid Powerlink 275kV network
Contract Sum Approx. A$1.1 billion combined
Target Completion End of 2028

Smoky Creek solar project moves into major package delivery

TCL Solar formally announced the module-supply award on 29 July 2026 as preparations continued for delivery of the two adjacent power stations.

The module award matters because it provides another visible marker of the project’s transition from development and financing into physical procurement.

The Smoky Creek solar project now has a principal EPC contractor, secured financing, long-term industrial offtake arrangements and major equipment packages progressing toward construction.

Smoky Creek solar project utility-scale solar construction near Biloela in Central Queensland
Illustrative editorial image. Not an official construction photograph.
Package Significance

One package in a much larger delivery program

A 720MWp module order is substantial by itself, but the commercial opportunity around Smoky Creek and Guthrie’s Gap extends through civil construction, battery infrastructure, electrical works, high-voltage connection, logistics, plant hire and regional workforce support.

Each large equipment award also increases certainty around the overall construction sequence and brings subsequent installation and support activities closer.

A $1.1 billion dual-site construction program near Biloela

The scale of the Smoky Creek solar project goes well beyond the newly awarded module-supply package.

DT Infrastructure is the engineering, procurement and construction contractor for the two neighbouring power stations being developed by Edify Energy in Central Queensland.

Edify places the development approximately 40 kilometres north of Biloela and 75 kilometres south of Rockhampton, across approximately 1,800 hectares of cleared land.

DT Infrastructure’s parent company, Gamuda , lists a combined contract sum of approximately A$1.1 billion and a current completion target of the end of 2028.

Edify Energy reached financial close on the developments in May 2026, establishing the funding position for the current delivery program.

DT Infrastructure’s EPC scope extends across civil, solar, battery and HV works

Delivery of the Smoky Creek solar project requires a broad combination of civil, renewable-energy, battery and high-voltage infrastructure capability.

DT Infrastructure’s published scope includes:
  • 600MW AC connection
  • 720MWp photovoltaic solar farm
  • 600MW / 2,400MWh battery storage
  • Site civil works
  • Site benching
  • Internal infrastructure
  • New 33kV / 275kV substation
  • Two 370MVA transformers
  • Solar tracking infrastructure
  • Module installation
  • Electrical infrastructure
  • Temporary works
  • Site establishment
  • Project fencing
  • Testing and commissioning
  • Two years of O&M services

This places the project firmly in major-project territory for Queensland contractors operating across construction, energy, logistics and industrial supply-chain services.

The package sequence is becoming clearer

  • March 2025 — long-term industrial offtake secured Rio Tinto entered 20-year solar and battery hybrid services agreements with Edify Energy.
  • March 2026 — DT Infrastructure selected DT Infrastructure was selected as preferred EPC contractor.
  • May 2026 — financial close and EPC delivery confirmed Edify Energy reached financial close and DT Infrastructure confirmed its delivery role.
  • Mid-2026 — battery supply progresses Major battery equipment arrangements progressed for the project’s 2,400MWh BESS.
  • 29 July 2026 — TCL Solar module package announced TCL Solar confirmed the 720MWp photovoltaic module supply award.
  • Early Q2 2027 — module installation expected TCL Solar says module installation is expected to begin in early Q2 2027.
  • End of 2028 — current completion target The dual-site development is currently targeting completion by the end of 2028.
Energy Storage

2.4GWh makes storage a major part of the build

The development includes a 600MW / 2,400MWh battery energy storage system, making the battery component a major construction and electrical workstream rather than a secondary addition to the solar farm.

Battery delivery creates interfaces across civil foundations, electrical balance-of-plant, cabling, controls, communications, commissioning, fire systems and high-voltage infrastructure.

Smoky Creek solar project battery energy storage and high-voltage substation infrastructure in Central Queensland
Illustrative BBI image representing utility-scale battery and electrical infrastructure.

Contractor opportunity extends far beyond the solar modules

The TCL award removes one significant equipment package from the Smoky Creek solar project pipeline, but the scale and duration of DT Infrastructure’s overall EPC scope means the supply-chain opportunity is substantially broader.

DT Infrastructure has indicated that around 800 jobs are associated with the project and that local contractor participation will support delivery and the regional economy.

For Biloela, Rockhampton, Gladstone and the broader Central Queensland industrial supply chain, the project potentially touches a wide range of capabilities.

Opportunities for Industry Capability areas relevant to project delivery
Bulk earthworks
Site benching
Access roads
Drainage works
Surveying
Geotechnical services
Solar piling
Tracker installation
Module installation
BESS installation
Electrical cabling
HV construction
33kV infrastructure
275kV works
Substation construction
Transformer installation
Controls & communications
Testing & commissioning
Temporary facilities
Fencing & security
Crane & lifting
Heavy haulage
Freight & logistics
Plant hire
Fuel services
Workforce services
Environmental services
Procurement note: These are capability areas associated with the published EPC scope and likely delivery interfaces. They should not be interpreted as confirmation that every item is currently available as a separate subcontract or tender package. Businesses should verify live procurement opportunities directly with DT Infrastructure, Edify Energy or an authorised project procurement channel.

The 275kV connection adds another layer of project complexity

The Smoky Creek solar project and neighbouring Guthrie’s Gap development are designed as an integrated solar-and-storage system connected to Powerlink’s 275kV transmission network.

The first stage includes a 600MW AC connection while the solar array itself provides 720MWp of installed photovoltaic capacity.

The development incorporates utility-scale battery infrastructure, a new substation, large step-up transformers, electrical reticulation, controls and transmission interfaces.

This is therefore materially more complex than simply constructing a large field of photovoltaic modules.

Smoky Creek solar project module installation and renewable energy construction activity in Central Queensland
Illustrative BBI project image. Module installation is expected from early Q2 2027.
Construction Outlook

Module installation creates the next visible construction milestone

TCL Solar says installation of its photovoltaic modules is expected to commence in early Q2 2027.

Before and around that milestone, key delivery activities include site preparation, piling, trackers, electrical works, logistics, lifting and supporting construction services.

Rio Tinto connects the project directly with Gladstone heavy industry

The commercial foundation behind the development also has major relevance to Central Queensland industry.

Rio Tinto has entered long-term agreements covering 90% of the solar power and battery-storage capacity generated by Smoky Creek and Guthrie’s Gap.

The arrangements form part of Rio Tinto’s strategy to repower its Gladstone industrial operations, including the Boyne aluminium smelter.

The commercial importance of the Smoky Creek solar project therefore extends beyond renewable generation, linking new Central Queensland energy infrastructure directly with major industrial demand in Gladstone.

Regional delivery opportunity across Central Queensland

The Smoky Creek solar project is moving from planning into procurement and construction, increasing its relevance to the Central Queensland supply chain.

Large projects of this scale rarely reach completion through a principal contractor and a small number of major equipment vendors alone.

Delivery typically depends on layers of civil construction, electrical installation, logistics, temporary works, equipment hire, technical services, workforce support and commissioning.

The commercial significance extends beyond the TCL Solar award.

The approximately $1.1 billion Central Queensland development now has a named EPC contractor, financial close, major equipment supply progressing, a long-term industrial customer and a defined construction horizon.

Project Delivery Outlook

Major equipment awards are moving the dual-site project deeper into delivery

Smoky Creek and Guthrie’s Gap now combine a principal EPC contractor, secured financing, long-term industrial offtake, major solar procurement, 2.4GWh of battery storage, a 275kV grid interface and a current completion target extending through 2028.

The TCL Solar module package is one component of a much broader EPC program spanning civil construction, solar installation, battery infrastructure and high-voltage works.

Each major equipment award increases definition around the construction sequence and brings subsequent installation, logistics and commissioning activities closer.

Near-term delivery indicators include site mobilisation, earthworks, solar piling, tracker installation, module deliveries, BESS installation, 33kV and 275kV works, transformer delivery and testing and commissioning.

The main supply-chain interfaces extend across civil construction, electrical installation, solar assembly, battery infrastructure, HV works, logistics and regional project services.

What businesses should watch next

DT Infrastructure supplier engagement
Site mobilisation
Major earthworks activity
Civil and drainage packages
Solar piling packages
Tracker installation
TCL module deliveries
Module installation
Battery-system delivery
BESS installation
33kV works
275kV interface works
Transformer delivery
Heavy lift requirements
Plant and equipment hire
Local workforce recruitment
Testing and commissioning
O&M transition
BBI Industry Directory

Find Queensland firms positioned for major project work

Search engineering, civil construction, equipment hire, logistics, fabrication and industrial service capability across Queensland’s major project regions.

With solar modules now awarded and 2.4GWh of battery storage forming a major part of the build, which delivery stream is likely to create the strongest regional opportunity — civil works, solar installation, battery infrastructure or high-voltage construction?

Sources

  1. DT Infrastructure — Smoky Creek and Guthrie’s Gap Solar Power Stations
  2. DT Infrastructure — Central Queensland solar and battery EPC contract award
  3. Edify Energy — Smoky Creek & Guthrie’s Gap project profile
  4. Edify Energy — Financial close on Smoky Creek and Guthrie’s Gap
  5. TCL Solar — 720MW module supply contract announcement
  6. Gamuda — Smoky Creek and Guthrie’s Gap project scope and contract value
  7. Rio Tinto — Edify Energy solar and battery agreement for Gladstone operations
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information available at the date of publication. References to potential contractor, subcontractor, supplier, employment or service opportunities are general industry observations based on the published project scope and do not represent confirmation that individual packages are currently open for tender, nor that any particular business will be engaged by Edify Energy, DT Infrastructure, TCL Solar, Powerlink or another project participant. Project values, schedules, procurement arrangements and technical scope may change as delivery progresses. Businesses should verify current project information, supplier registration requirements and procurement opportunities directly with the project owner, principal contractor or authorised procurement channel. Illustrative images used in this article are editorial visualisations and should not be interpreted as official photographs of current Smoky Creek or Guthrie’s Gap construction activity.