Industry engagement — 14 August 2026

The next section of Queensland’s Coomera Connector is going to industry.

The Queensland Government has opened industry engagement for Coomera Connector Stage 2, moving the next approximately 5km section of the future M9 between Pimpama and Coomera deeper into planning and design.

The current procurement is an Early Tenderer Involvement process, bringing major construction capability alongside the Department of Transport and Main Roads before the project reaches a future main-works stage.

Stage 2 will extend the motorway north from Stage 1 at Shipper Drive in Coomera to Yawalpah Road at Pimpama, with major road, interchange, bridge and active-transport interfaces already identified in the developing scope.

Stage 2 does not yet have a published construction value: Queensland has funded planning and design, while funding for Stage 2 delivery remains subject to future Australian and Queensland Government decisions.

Coomera Connector Stage 2 industry EOI Project Watch showing the approximately 5km Pimpama to Coomera motorway section entering early industry engagement
BBI Project Watch — industry engagement has opened for the next approximately 5km Coomera Connector Stage 2 section.
Project Pulse Early Tenderer Involvement
~5km Stage 2 Length
M9 Coomera Connector
EOI Industry Engagement Open
45km Full Future Corridor
TBC Stage 2 Delivery Funding
Fresh procurement milestone — 14 August 2026 Queensland has opened expressions of interest for industry participation in the design development of Coomera Connector Stage 2 between Yawalpah Road at Pimpama and Shipper Drive at Coomera.

The announcement forms part of the new Gold Coast Transport Plan and moves the next Coomera Connector section beyond internal planning into a more commercially significant phase of industry involvement.

TMR’s project page describes Stage 2 as the next priority section of the future motorway for planning and design.

This is Early Tenderer Involvement — not a construction contract award

ETI Current Procurement Phase

Construction expertise is being brought into the project before main works through the Early Tenderer Involvement process.

Current tender information describes the process as Early Tenderer Involvement in relation to the future construction of Coomera Connector Stage 2.

The Government says early industry participation will help strengthen the design, improve cost certainty and make Stage 2 delivery-ready.

The distinction is important because Early Tenderer Involvement occurs before a main construction contract is awarded.

An ETI process can give major delivery contractors input into constructability, staging, methodology, risk, market capacity and cost before the final delivery model and construction package are locked down.

It does not mean Stage 2 construction has already been awarded.

Supplier-access clarification: This EOI is an upstream major-contractor procurement process rather than an open request for every civil subcontractor or supplier to submit directly. Current tender reporting identifies significant TMR road and bridge prequalification requirements. Smaller contractors and suppliers should follow the process because downstream opportunities may emerge later through shortlisted or appointed major contractors.
Project Snapshot
Project Coomera Connector Stage 2
Motorway Coomera Connector M9
Procuring Agency Department of Transport and Main Roads
Location Pimpama to Coomera, Gold Coast
Southern Limit Shipper Drive, Coomera
Northern Limit Yawalpah Road, Pimpama
Length Approximately 5km
Current Phase Planning, design and Early Tenderer Involvement
Current Funding Planning and design funded
Construction Funding Not yet committed
Full M9 Corridor Approximately 45km Loganholme to Nerang
Future Combined Stage 1 + 2 Approximately 21km Pimpama to Nerang
Illustrative location graphic for Coomera Connector Stage 2 between Pimpama and Coomera on the northern Gold Coast
Illustrative BBI location graphic only. It is not an official TMR alignment map. The Coomera Connector is officially designated M9 and runs east of the existing M1.
Pimpama → Coomera

Stage 2 extends the operating and under-construction motorway further north

The new section will connect into Stage 1 at Shipper Drive and continue approximately 5km north toward Pimpama.

Once Stage 2 is ultimately delivered, the Stage 1 and Stage 2 motorway sections would create approximately 21km of Coomera Connector from Pimpama through to Nerang.

Stage 2 already carries major road, bridge and interchange interfaces

Although final design is still being refined, the developing project scope gives industry a clear indication of the type of infrastructure involved.

Mainline ~5km Motorway

Extension of the M9 north from the Stage 1 connection at Shipper Drive.

Interchange Foxwell Road

Grade-separated motorway and local-road interface in the Coomera growth area.

Northern Connection Yawalpah Road

Stage 2 connection at Pimpama with provision for future continuation north.

Structures Oakey Creek

Bridge infrastructure associated with Oakey Creek and adjoining wetland areas.

Structures McCoys Creek

Additional bridge infrastructure forms part of the developing Stage 2 scope.

Active Transport Shared Path

Walking and cycling infrastructure with links into the surrounding local-road network.

Infrastructure Partnerships Australia’s current project profile also identifies overpass structures around Foxwell Road and Oakey Creek Road.

That creates meaningful engineering interfaces across motorway earthworks, structures, drainage, pavement design, utilities, environmental management and local-road tie-ins before detailed design is finalised.

Stage 2 has planning money — not yet a construction budget

TMR is explicit that Stage 2 is currently a planned investment.

Queensland has allocated funding toward planning and design, but funding for physical delivery will be considered by the Australian and Queensland governments later.

That future decision remains subject to project development, investigations and funding negotiations.

Funding clarification: The $3.5 billion Stage 1 value — and historic estimates for the wider Coomera Connector — do not represent the value of Stage 2. No current Stage 2 construction funding package has been committed publicly. The current status is: planning and design funded; construction value TBC.
Future Construction

The EOI is shaping a future build — Stage 2 construction has not started

Large motorway delivery could eventually create a significant civil and structures program across the northern Gold Coast.

But the current milestone remains pre-construction.

Industry is being engaged now so TMR can improve constructability, refine design, understand risk and strengthen future cost certainty before delivery funding is finalised.

Illustrative motorway construction representing the future civil works that could follow Coomera Connector Stage 2 planning and design
Illustrative BBI future-construction image. Coomera Connector Stage 2 remains in planning, design and Early Tenderer Involvement and is not currently under main construction.

The $3.5B Stage 1 program shows the scale of motorway delivery — but it is a separate funded project

Stage 2 sits immediately north of the major Stage 1 Coomera-to-Nerang program.

Stage 1 is approximately 16km and is being delivered through North, Central and South packages with total current investment of approximately $3.5 billion.

Coomera Connector Stage 1 context
~16km Total Stage 1 corridor from Coomera to Nerang.
$3.5B Current Stage 1 investment — not Stage 2 funding.
North Open Shipper Drive to Helensvale Road is carrying traffic.
Central + South Remaining Stage 1 packages continue through construction.

The open Stage 1 North section gives Stage 2 a direct physical connection to an operating motorway segment rather than an isolated future corridor.

However, it would be misleading to describe the entire $3.5 billion Stage 1 program as complete or imply that Stage 2 shares that funding envelope.

Early Tenderer Involvement creates a different opportunity from downstream subcontracting

The current EOI sits at the top of the project delivery chain.

Major road and bridge contractors participating in ETI can help TMR test construction methodology, staging, design assumptions, major risks, program and market conditions.

That work can influence how the eventual construction contract is structured and, later, how packages flow through the civil supply chain.

01
Planning TMR develops the Stage 2 corridor and reference design.
02
ETI EOI Major industry teams enter early procurement.
03
Design Refinement Constructability, risk, staging and cost certainty improve.
04
Funding Governments consider future Stage 2 delivery funding.
05
Main Delivery Future contract award unlocks broader subcontract procurement.
Coomera Connector Stage 2 industry engagement graphic explaining the EOI planning and design phase between Pimpama and Coomera
BBI editorial procurement summary. This graphic is not an official TMR tender notice; contractors should use official Queensland Government procurement channels for eligibility and submission requirements.
Procurement Signal

For most suppliers, the important opportunity comes after this upstream EOI

The immediate process is aimed at major industry teams with the capability and TMR prequalification required for a motorway of this scale.

Smaller civil contractors, suppliers and specialist firms should still follow the ETI because the teams that emerge from the process may ultimately become the gateway to downstream construction packages.

If Stage 2 reaches construction, the supply chain could span the full motorway civil stack

The following areas are derived from the publicly described physical scope and normal requirements of a major motorway project.

They are future capability areas to monitor, not confirmation of currently open subcontract packages.

Future Contractor Exposure Capability potentially relevant if Coomera Connector Stage 2 moves into main construction
Bulk earthworks
Cut & fill
Excavation
Ground improvement
Piling
Bridge foundations
Bridge structures
Precast bridge elements
Structural concrete
Reinforcement
Structural steel
Retaining walls
Road pavements
Roadbase
Asphalt
Drainage
Culverts
Stormwater infrastructure
Creek crossings
Wetland interfaces
Erosion control
Sediment control
Environmental monitoring
Fauna management
Utility relocations
Water services
Electrical relocations
Telecommunications
Street lighting
ITS infrastructure
Traffic signals
Variable message signs
Road barriers
Guardrail
Noise barriers
Line marking
Road signage
Traffic management
Temporary roads
Active transport path
Shared-path bridges
Surveying
Geotechnical investigation
Materials testing
Concrete testing
Plant hire
Excavator hire
Dozer hire
Grader hire
Crane hire
Heavy haulage
Quarry materials
Fuel supply
Construction logistics
Rehabilitation & landscaping
Procurement note: Coomera Connector Stage 2 remains in planning, design and Early Tenderer Involvement. Queensland has not yet announced a main construction contract or committed Stage 2 delivery funding. The contractor and supplier areas above identify potential future workstreams based on the developing motorway scope. These future workstreams should not be interpreted as currently open tenders or subcontract packages.
Procurement Access The current opportunity sits within TMR’s major-project procurement framework

Major TMR road contracts typically require relevant contractor and financial prequalification, and the current Stage 2 ETI should be viewed in that context.

Businesses outside the immediate ETI eligibility group should monitor which major teams progress and prepare for later subcontract, materials and specialist-service procurement if the project moves into funded delivery.

QTenders and TMR project notices remain the appropriate sources for formal procurement information.

The EOI matters because Stage 2 is the next physical extension of a live multibillion-dollar motorway program

Stage 2 is not a disconnected planning exercise.

It will connect directly into the Stage 1 North motorway at Shipper Drive and extend the network deeper into the rapidly developing northern Gold Coast.

TMR says the overall 45km M9 is intended to provide an alternative north-south corridor east of the M1 between Loganholme and Nerang.

The Government’s new Gold Coast Transport Plan also places Stage 2 alongside a broader program of motorway interchange, bridge, active-transport and public-transport investment ahead of Brisbane 2032.

Project Delivery Outlook

Early Tenderer Involvement moves Stage 2 closer to a delivery-ready design

Stage 2 does not yet have committed construction funding or a confirmed main-works value, but TMR has begun involving major delivery contractors before main construction procurement.

Early industry participation can influence constructability, risk allocation, staging, cost certainty and the eventual contract structure.

The developing physical scope already includes approximately 5km of motorway, interchange works, bridge structures, local-road connections and active-transport infrastructure.

The adjoining Stage 1 program provides direct delivery context, while remaining financially separate from Stage 2.

The next major delivery sequence is: ETI participation → refined design → delivery funding → main contractor structure → downstream civil and supply packages.

Key milestones ahead include the outcome of the ETI process, updated project cost information, government delivery funding and future main-works procurement.

What businesses should watch next

ETI respondent teams
Shortlisted industry groups
Refined Stage 2 design
Foxwell Road interchange design
Yawalpah Road connection
Oakey Creek bridge design
McCoys Creek bridge design
Environmental approvals
Geotechnical investigations
Utility-relocation planning
Property acquisition
Final motorway staging
Updated cost estimate
Australian Government funding
Queensland delivery funding
Main delivery model
Future main-works procurement
Earthworks packages
Bridge packages
Drainage packages
Pavement packages
Quarry-material demand
Plant-hire demand
Downstream supplier engagement

Related BBI Project Watch

BBI Industry Directory

Find South East Queensland firms supporting major road projects

Search civil contractors, engineers, equipment providers, fabricators and logistics businesses supporting major road, bridge and transport infrastructure across South East Queensland.

With Coomera Connector Stage 2 now bringing major contractors into Early Tenderer Involvement, which future package could create the strongest South East Queensland opportunity — bulk earthworks, bridges, pavements, drainage or plant and materials supply?

Sources

  1. Queensland Government — Coomera Connector Stage 2 to get commuters home sooner and safer, 14 August 2026
  2. Department of Transport and Main Roads — Coomera Connector Stage 2, Pimpama to Coomera
  3. Department of Transport and Main Roads — Coomera Connector program
  4. Infrastructure Partnerships Australia — Coomera Connector Stage Two project profile
  5. Department of Transport and Main Roads — Gold Coast Transport Plan
  6. Queensland Government — QTenders
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information current at the date of publication. Coomera Connector Stage 2 is currently in planning, design and industry-engagement phases. The Queensland Government has allocated funding toward Stage 2 planning and design. Funding for physical construction and delivery has not yet been committed and will be considered by the Australian and Queensland governments subject to further project development, investigations and funding negotiations. No Stage 2 construction value is presented because physical delivery funding has not yet been committed. The approximately $3.5 billion figure associated with Coomera Connector Stage 1 relates to the separately funded approximately 16km Coomera-to-Nerang program and must not be interpreted as the value of Stage 2. Stage 1 North between Shipper Drive and Helensvale Road is open to traffic, while other Stage 1 packages remain under construction. The current Stage 2 procurement is an early industry-engagement / Early Tenderer Involvement process. It is not a main Stage 2 construction-contract award and should not be interpreted as an open subcontract opportunity for all suppliers. References to potential future contractor, subcontractor and supplier workstreams are general observations based on publicly described motorway, interchange, bridge and active-transport scope and typical requirements associated with major road construction. The downstream workstreams identified in this article should not be interpreted as currently open tender packages. Final alignment, scope, delivery model, project cost, funding, package boundaries and construction timing may change as design development, environmental assessment and government investment decisions progress. Images used in this article are BBI editorial graphics and visualisations. They should not be interpreted as official TMR alignment maps, current Stage 2 construction photographs or Queensland Government tender notices unless separately identified. Businesses should verify current eligibility, prequalification requirements, closing dates and procurement documentation directly through TMR, QTenders and other authorised Queensland Government procurement channels.
Project information reviewed against Queensland Government, Department of Transport and Main Roads and current infrastructure procurement information — 15 August 2026.