The next section of Queensland’s Coomera Connector is going to industry.
The Queensland Government has opened industry engagement for Coomera Connector Stage 2, moving the next approximately 5km section of the future M9 between Pimpama and Coomera deeper into planning and design.
The current procurement is an Early Tenderer Involvement process, bringing major construction capability alongside the Department of Transport and Main Roads before the project reaches a future main-works stage.
Stage 2 will extend the motorway north from Stage 1 at Shipper Drive in Coomera to Yawalpah Road at Pimpama, with major road, interchange, bridge and active-transport interfaces already identified in the developing scope.
Stage 2 does not yet have a published construction value: Queensland has funded planning and design, while funding for Stage 2 delivery remains subject to future Australian and Queensland Government decisions.

The announcement forms part of the new Gold Coast Transport Plan and moves the next Coomera Connector section beyond internal planning into a more commercially significant phase of industry involvement.
TMR’s project page describes Stage 2 as the next priority section of the future motorway for planning and design.
This is Early Tenderer Involvement — not a construction contract award
Construction expertise is being brought into the project before main works through the Early Tenderer Involvement process.
Current tender information describes the process as Early Tenderer Involvement in relation to the future construction of Coomera Connector Stage 2.
The Government says early industry participation will help strengthen the design, improve cost certainty and make Stage 2 delivery-ready.
The distinction is important because Early Tenderer Involvement occurs before a main construction contract is awarded.
An ETI process can give major delivery contractors input into constructability, staging, methodology, risk, market capacity and cost before the final delivery model and construction package are locked down.
It does not mean Stage 2 construction has already been awarded.

Stage 2 extends the operating and under-construction motorway further north
The new section will connect into Stage 1 at Shipper Drive and continue approximately 5km north toward Pimpama.
Once Stage 2 is ultimately delivered, the Stage 1 and Stage 2 motorway sections would create approximately 21km of Coomera Connector from Pimpama through to Nerang.
Stage 2 already carries major road, bridge and interchange interfaces
Although final design is still being refined, the developing project scope gives industry a clear indication of the type of infrastructure involved.
Extension of the M9 north from the Stage 1 connection at Shipper Drive.
Grade-separated motorway and local-road interface in the Coomera growth area.
Stage 2 connection at Pimpama with provision for future continuation north.
Bridge infrastructure associated with Oakey Creek and adjoining wetland areas.
Additional bridge infrastructure forms part of the developing Stage 2 scope.
Walking and cycling infrastructure with links into the surrounding local-road network.
Infrastructure Partnerships Australia’s current project profile also identifies overpass structures around Foxwell Road and Oakey Creek Road.
That creates meaningful engineering interfaces across motorway earthworks, structures, drainage, pavement design, utilities, environmental management and local-road tie-ins before detailed design is finalised.
Stage 2 has planning money — not yet a construction budget
TMR is explicit that Stage 2 is currently a planned investment.
Queensland has allocated funding toward planning and design, but funding for physical delivery will be considered by the Australian and Queensland governments later.
That future decision remains subject to project development, investigations and funding negotiations.
The EOI is shaping a future build — Stage 2 construction has not started
Large motorway delivery could eventually create a significant civil and structures program across the northern Gold Coast.
But the current milestone remains pre-construction.
Industry is being engaged now so TMR can improve constructability, refine design, understand risk and strengthen future cost certainty before delivery funding is finalised.

The $3.5B Stage 1 program shows the scale of motorway delivery — but it is a separate funded project
Stage 2 sits immediately north of the major Stage 1 Coomera-to-Nerang program.
Stage 1 is approximately 16km and is being delivered through North, Central and South packages with total current investment of approximately $3.5 billion.
The open Stage 1 North section gives Stage 2 a direct physical connection to an operating motorway segment rather than an isolated future corridor.
However, it would be misleading to describe the entire $3.5 billion Stage 1 program as complete or imply that Stage 2 shares that funding envelope.
Early Tenderer Involvement creates a different opportunity from downstream subcontracting
The current EOI sits at the top of the project delivery chain.
Major road and bridge contractors participating in ETI can help TMR test construction methodology, staging, design assumptions, major risks, program and market conditions.
That work can influence how the eventual construction contract is structured and, later, how packages flow through the civil supply chain.

For most suppliers, the important opportunity comes after this upstream EOI
The immediate process is aimed at major industry teams with the capability and TMR prequalification required for a motorway of this scale.
Smaller civil contractors, suppliers and specialist firms should still follow the ETI because the teams that emerge from the process may ultimately become the gateway to downstream construction packages.
If Stage 2 reaches construction, the supply chain could span the full motorway civil stack
The following areas are derived from the publicly described physical scope and normal requirements of a major motorway project.
They are future capability areas to monitor, not confirmation of currently open subcontract packages.
Major TMR road contracts typically require relevant contractor and financial prequalification, and the current Stage 2 ETI should be viewed in that context.
Businesses outside the immediate ETI eligibility group should monitor which major teams progress and prepare for later subcontract, materials and specialist-service procurement if the project moves into funded delivery.
QTenders and TMR project notices remain the appropriate sources for formal procurement information.
The EOI matters because Stage 2 is the next physical extension of a live multibillion-dollar motorway program
Stage 2 is not a disconnected planning exercise.
It will connect directly into the Stage 1 North motorway at Shipper Drive and extend the network deeper into the rapidly developing northern Gold Coast.
TMR says the overall 45km M9 is intended to provide an alternative north-south corridor east of the M1 between Loganholme and Nerang.
The Government’s new Gold Coast Transport Plan also places Stage 2 alongside a broader program of motorway interchange, bridge, active-transport and public-transport investment ahead of Brisbane 2032.
Early Tenderer Involvement moves Stage 2 closer to a delivery-ready design
Stage 2 does not yet have committed construction funding or a confirmed main-works value, but TMR has begun involving major delivery contractors before main construction procurement.
Early industry participation can influence constructability, risk allocation, staging, cost certainty and the eventual contract structure.
The developing physical scope already includes approximately 5km of motorway, interchange works, bridge structures, local-road connections and active-transport infrastructure.
The adjoining Stage 1 program provides direct delivery context, while remaining financially separate from Stage 2.
The next major delivery sequence is: ETI participation → refined design → delivery funding → main contractor structure → downstream civil and supply packages.
Key milestones ahead include the outcome of the ETI process, updated project cost information, government delivery funding and future main-works procurement.
What businesses should watch next
Related BBI Project Watch
Find South East Queensland firms supporting major road projects
Search civil contractors, engineers, equipment providers, fabricators and logistics businesses supporting major road, bridge and transport infrastructure across South East Queensland.
Sources
- Queensland Government — Coomera Connector Stage 2 to get commuters home sooner and safer, 14 August 2026
- Department of Transport and Main Roads — Coomera Connector Stage 2, Pimpama to Coomera
- Department of Transport and Main Roads — Coomera Connector program
- Infrastructure Partnerships Australia — Coomera Connector Stage Two project profile
- Department of Transport and Main Roads — Gold Coast Transport Plan
- Queensland Government — QTenders