Skip to main content

Bowen Basin Index

Project Watch EPC Contract Renewable Infrastructure Townsville
Financial close — August 2026

$569 million. 1.2GWh of battery storage. More than $450 million expected through regional communities and supply chains. Now the projects have financial close and DT Infrastructure has Notices to Proceed.

Edify Energy’s Ganymirra and Majors Creek solar and battery hybrid projects near Townsville have moved decisively from development toward physical delivery.

DT Infrastructure has secured the two Engineering, Procurement and Construction contracts, with a reported combined value of approximately A$569 million.

Together, the projects will deliver 360MWp of solar generation and a 300MW / 1,200MWh battery energy storage system, supported by a new substation and associated transmission connection infrastructure.

The projects have now passed several major commercial gates. Financial close has been reached, Notices to Proceed have been issued and major construction is expected to commence in Q3 2026.

Ganymirra and Majors Creek Project Watch showing DT Infrastructure securing approximately $569 million of EPC contracts near Townsville
BBI Project Watch — DT Infrastructure’s approximately $569M Ganymirra and Majors Creek EPC program.
Project Pulse Financial Close + EPC Commitment
$569M Combined EPC Value
360MWp Solar Generation
1.2GWh Battery Storage
~400 Construction Jobs
$450M+ Regional Economic Flow
Fresh commercial milestone — 12–13 August 2026 DT Infrastructure received Notices to Proceed for Ganymirra and Majors Creek on 12 August, followed by Edify Energy confirming financial close on the two hybrid projects on 13 August.

That combination materially changes the commercial position of the projects.

DT Infrastructure had already been selected as preferred EPC contractor earlier in 2026, while engineering and pre-construction work was underway.

The latest developments move the projects beyond preferred-contractor status and into committed EPC delivery.

$569M Combined EPC Contracts

Gamuda’s Australian subsidiary DT Infrastructure has entered two separate EPC contracts covering Ganymirra and Majors Creek.

Reporting from Gamuda’s market disclosure places each contract at approximately A$284.53 million, giving a combined value of approximately A$569 million.

This is the value of the two DT Infrastructure EPC contracts — not the total value of every financing facility, future adjacent battery project or wider Edify portfolio investment.

Financing clarification: Edify separately says approximately $3.2 billion of project financing has been committed across Ganymirra, Majors Creek, Smoky Creek and Guthrie’s Gap through a 14-lender portfolio financing platform. That $3.2 billion figure spans four projects and should not be presented as the financing value of Ganymirra and Majors Creek alone.
Project Snapshot
Projects Ganymirra & Majors Creek Solar Power Stations
Developer Edify Energy
EPC Contractor DT Infrastructure
Parent Company Gamuda Berhad
Location Woodstock / Majors Creek, Townsville region
Solar 360MWp combined
Battery 300MW / 1,200MWh integrated BESS
Battery Supplier CATL
Network / Connection Powerlink
EPC Contract Value Approximately A$569M combined
Major Construction Expected Q3 2026
Operations Edify targets 2028
Illustrative aerial view of the Ganymirra and Majors Creek solar and battery projects near Townsville following financial close
Illustrative BBI aerial visualisation representing the future Ganymirra and Majors Creek solar and BESS development. Financial close was announced on 13 August 2026; DT Infrastructure received Notices to Proceed on 12 August.
Financial Close

The financing milestone moves the projects deeper into delivery

Financial close is a materially stronger commercial milestone than development approval or preferred-contractor selection alone.

It confirms the financing arrangements required to support project delivery have been completed, while DT Infrastructure’s Notices to Proceed allow EPC execution to advance.

Edify says a syndicate of 14 domestic and international lenders supports its broader renewable-energy financing platform.

Ganymirra and Majors Creek combine solar, storage and grid infrastructure

The Ganymirra and Majors Creek projects are being delivered as integrated hybrid energy assets rather than conventional standalone solar farms.

Together they combine 360MWp of photovoltaic generation with 300MW / 1,200MWh of lithium-ion battery storage.

The projects use reverse DC-coupled architecture, allowing solar and battery systems to operate behind a common set of grid-forming inverters.

360MWp Combined photovoltaic solar-generation capacity.
300MW Integrated battery discharge power.
1,200MWh Four-hour battery energy-storage capacity.
Grid Forming Inverters designed to contribute system stability and resilience.

DT Infrastructure’s announced project scope also includes a new substation and associated transmission connection infrastructure.

That makes this materially more complex than simply installing solar modules and battery containers.

The core delivery team is now defined

Developer / Owner Edify Energy
EPC Contractor DT Infrastructure
Battery Supplier CATL
Network & Connection Powerlink Queensland

Edify identifies DT Infrastructure as the EPC contractor, CATL as battery supplier and Powerlink as the head contractor for network and connection works.

The named delivery participants also provide greater clarity on where future procurement and subcontracting interfaces may sit.

Important: these are not the same scope as the additional 2GWh CIS Tender 8 batteries

Two different Ganymirra / Majors Creek battery programs are now in the market.

The projects reaching financial close in August combine 360MWp of solar generation with a total 300MW / 1,200MWh integrated battery system.

Separately, Edify was selected under Capacity Investment Scheme Tender 8 in June 2026 for the Ganymirra Energy Storage System and Majors Creek Energy Storage System — two additional 250MW / 1,000MWh batteries.

Those newer batteries total another 500MW / 2,000MWh and are proposed to be built adjacent to the hybrid solar/BESS plants.

The separate Tender 8 battery selections are covered in BBI’s broader Queensland battery-project pipeline analysis .

The August financial-close milestone covered here relates specifically to the original Ganymirra and Majors Creek hybrid power stations, including Notices to Proceed and approximately $569 million of DT Infrastructure EPC contracts.

EPC Delivery

Major construction is expected in Q3 2026

DT Infrastructure says early engineering and pre-construction activities are already underway.

Major construction is expected to commence during the third quarter of 2026, creating the next visible project milestone.

Gamuda’s market disclosure indicates the EPC delivery period extends through to January 2029.

Illustrative DT Infrastructure construction activity for Ganymirra and Majors Creek with battery equipment crane lifting and EPC works
Illustrative BBI construction image representing DT Infrastructure’s EPC scope. It is not an official photograph of current Ganymirra or Majors Creek site works.

Solar and battery EPC creates a broad physical construction program

Large hybrid renewable projects require much more than the supply of solar modules and battery units.

Before the assets can operate, DT Infrastructure must integrate civil works, solar infrastructure, battery systems, electrical balance of plant, substations, network interfaces, controls and commissioning.

The fact that the projects are being built as integrated DC-coupled hybrid assets adds further electrical and controls complexity.

$450M+ regional-flow expectation places major focus on local procurement

Edify expects approximately 400 local construction jobs and says more than $450 million should flow into local communities through regional supply chains, local employment, First Nations businesses and associated economic activity.

This represents a significant regional-supply-chain commitment for a major North Queensland energy development.

Contractor Areas to Watch Capability relevant to delivery of Ganymirra and Majors Creek
Site establishment
Bulk earthworks
Clearing & grubbing
Access roads
Internal roads
Stormwater drainage
Hardstands
Surveying
Geotechnical services
Solar piling
Tracker installation
Solar module installation
BESS foundations
Battery installation
Inverter installation
Transformer installation
Electrical balance of plant
LV electrical
MV electrical
HV electrical
Cable trenches
Underground cabling
Substation civil works
Substation installation
Switchgear
Protection & control
SCADA
Communications
Network integration
Transmission interfaces
Fire detection
Fire protection
Security fencing
CCTV & access control
Temporary facilities
Crane & lifting
Heavy haulage
Freight & logistics
Plant hire
Fuel supply
Water carts
Environmental services
Waste management
First Nations businesses
Workforce accommodation
Local transport
Testing & commissioning
Operations & maintenance
Procurement note: The areas above are capability streams associated with utility-scale solar, BESS and grid-connection delivery and should not be interpreted as confirmation that every item is currently available as an individual DT Infrastructure subcontract package. Some major equipment and network scopes are already assigned, including CATL’s battery role and Powerlink’s network and connection role. Businesses should verify active package status directly through authorised procurement channels.
Contractor & Supplier Pathway DT Infrastructure operates supplier procurement through SAP Ariba

DT Infrastructure operates a digital procurement system for sourcing, contracting and managing vendors, contractors and consultants.

The company states that supplier sourcing and management is handled through SAP Ariba and provides an online registration pathway for businesses interested in joining its procurement platform.

With more than $450 million expected to flow through regional communities and supply chains across the Ganymirra and Majors Creek development, North Queensland businesses should ensure their supplier information, insurances, capability documentation and compliance records are ready before relevant packages are released.

Illustrative Ganymirra and Majors Creek project sign showing 360MWp solar 300MW 1200MWh BESS and DT Infrastructure EPC delivery
Illustrative BBI project sign. It is not presented as an official on-site DT Infrastructure or Edify Energy sign.
Regional Supply Chain

More than $450M is expected to flow through regional communities

Edify’s regional commitment extends beyond direct construction employment.

The developer identifies local procurement, First Nations participation, workforce capability, local employment and associated regional economic activity as core benefit-sharing pathways.

For Townsville-region contractors, the regional commitment adds a substantial local procurement and workforce dimension to the project’s overall scale.

The projects have now moved through the key commercial gates

December 2024 Original CIS agreements Ganymirra and Majors Creek hybrid solar and battery projects secure Capacity Investment Scheme support.
March 2026 DT Infrastructure selected DTI is announced as preferred EPC contractor for the Townsville hybrid projects.
24 June 2026 Separate Tender 8 batteries selected Additional Ganymirra and Majors Creek 250MW / 1,000MWh battery projects are selected under CIS Tender 8.
12 August 2026 Notices to Proceed DT Infrastructure receives the Notices to Proceed for the two EPC contracts.
13 August 2026 Financial close Edify announces financial close on the 360MWp solar and 1.2GWh integrated hybrid projects.
Q3 2026 Major construction expected DTI says early engineering and pre-construction is underway before major construction.
2028 Edify operational target Edify expects the projects to be operational and capable of supplying electricity equivalent to more than 100,000 homes.
January 2029 DTI contract completion horizon Gamuda’s market disclosure identifies January 2029 as the construction-contract completion horizon.

DT Infrastructure now has two major Edify EPC programs underway in Queensland

The award strengthens an existing relationship between DT Infrastructure and Edify Energy.

DT Infrastructure is also delivering Edify’s much larger Smoky Creek and Guthrie’s Gap solar and battery program near Biloela.

That Central Queensland development combines 720MWp of solar and 600MW / 2,400MWh of battery storage under an approximately $1.1 billion DT Infrastructure EPC program.

The addition of Ganymirra and Majors Creek therefore gives DT Infrastructure a substantial active renewable-energy order book across both Central and North Queensland.

Financial close and Notices to Proceed move the projects into committed delivery

Earlier project milestones established Capacity Investment Scheme support and identified DT Infrastructure as the preferred EPC contractor.

The August 2026 developments add financial close, executed EPC commitments and Notices to Proceed, providing substantially greater visibility on the delivery pathway ahead of expected major construction.

For broader context on Queensland’s Capacity Investment Scheme battery pipeline, see BBI’s Queensland battery-project pipeline analysis .

Project Delivery Outlook

$569M of EPC work is now moving toward major construction

The approximately $569 million figure represents the reported combined value of DT Infrastructure’s two EPC contracts, providing a defined measure of the committed construction scope.

DT Infrastructure now has two contracts, Notices to Proceed and a defined delivery role across solar, battery and associated infrastructure.

Edify has reached financial close, CATL is identified as battery supplier and Powerlink has responsibility for network and connection works.

The regional dimension is also significant: around 400 construction jobs and more than $450 million are expected to flow through regional communities and supply chains.

Relevant capability spans civil works, electrical construction, substations, logistics, plant hire, security, fire systems, workforce support and commissioning.

The next major commercial focus is the structure and timing of remaining supply-chain packages as major construction ramps up.

What businesses should watch next

DT Infrastructure supplier engagement
Q3 2026 major mobilisation
Bulk earthworks
Access-road construction
Solar piling
Tracker installation
Solar-module procurement
Battery-system deliveries
CATL equipment mobilisation
BESS foundations
Electrical balance of plant
Cable-trench works
Substation construction
Transformer delivery
Powerlink connection works
Protection and control
Grid-forming inverter commissioning
Fire-protection packages
Security and communications
Heavy lifting
Freight and logistics
Local workforce recruitment
First Nations supplier participation
Testing and commissioning
DTI operations and maintenance transition
Separate 2GWh Tender 8 batteries

Related BBI Project Watch

BBI Industry Directory

Find Townsville firms positioned for major energy projects

Search engineering, civil, electrical, equipment, logistics, fabrication and industrial-service businesses supporting solar, battery and grid infrastructure across Townsville and North Queensland.

With DT Infrastructure now holding approximately $569 million of EPC work and more than $450 million expected to flow through regional communities, which Ganymirra and Majors Creek workstream could create the strongest North Queensland contractor demand — civil construction, solar installation, BESS works, high-voltage infrastructure or logistics?

Sources

  1. Edify Energy — Edify secures financial close on Ganymirra and Majors Creek, 13 August 2026
  2. Gamuda — DT Infrastructure and Edify Energy strengthen renewable partnership with North Queensland solar projects, 13 August 2026
  3. Gamuda market announcement — Award of Ganymirra and Majors Creek EPC contracts
  4. The Edge Malaysia — Gamuda secures A$569M Ganymirra and Majors Creek EPC contracts
  5. Edify Energy — Ganymirra and Majors Creek project profile
  6. Edify Energy — Separate 500MW / 2,000MWh Ganymirra and Majors Creek battery projects, June 2026
  7. Australian Government — Capacity Investment Scheme Tender 8 outcomes
  8. DT Infrastructure — Supplier procurement and SAP Ariba registration
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information current at the date of publication. The approximately A$569 million figure refers to the reported combined value of DT Infrastructure’s two EPC contracts for the Ganymirra and Majors Creek hybrid solar and battery projects. It should not be interpreted as the total development value of all Edify Energy infrastructure at Woodstock, the value of Edify’s broader financing platform or the value of separate future Ganymirra and Majors Creek battery projects. Edify’s approximately $3.2 billion financing figure applies across a broader portfolio that includes Ganymirra, Majors Creek, Smoky Creek and Guthrie’s Gap. The 360MWp solar and 300MW / 1,200MWh BESS scope described in this article relates to the hybrid Ganymirra and Majors Creek power stations reaching financial close in August 2026. Separate Ganymirra Energy Storage System and Majors Creek Energy Storage System projects were selected under CIS Tender 8 in June 2026, with combined capacity of 500MW / 2,000MWh. Those additional battery projects are proposed adjacent to the hybrid plants and should not be automatically treated as part of the approximately $569 million EPC contract scope unless separately confirmed. References to potential contractor, subcontractor, supplier and service opportunities are general observations based on the published EPC scope and typical requirements associated with utility-scale solar, battery-storage and grid-connection construction. The capability areas identified in this article should not be interpreted as confirmation that each is currently available as an individual DT Infrastructure tender or subcontract package. Major equipment and connection roles may already be assigned, including CATL’s battery-supply role and Powerlink’s network and connection role. Businesses should verify live procurement opportunities and supplier requirements directly with DT Infrastructure, Edify Energy, Powerlink or authorised project procurement channels. Images used in this article are BBI editorial visualisations. They should not be interpreted as official photographs of current project construction, DT Infrastructure personnel, completed battery facilities or official on-site project signage.
Project information reviewed against Edify Energy, Gamuda / DT Infrastructure and Australian Government sources — 15 August 2026.