Project Watch Federal Assessment Swanbank 500MW / 2GWh BESS Pre-Construction
Ipswich grid-scale energy storage

Blackstone's 2GWh battery project has entered the federal process with a November construction target.

Octopus Australia's Blackstone Battery Energy Storage System has entered the federal EPBC process with a current proposed capacity of 500MW / 2,000MWh at Swanbank, in Ipswich's established energy and industrial precinct.

The referral sets out an unusually specific pre-construction sequence: complete financing and reach financial close, execute an EPC contract and Long-Term Service Agreement with Tesla, execute connection and access agreements with Powerlink Queensland and issue Notice to Proceed in Q4 2026.

Construction is currently expected to commence in November 2026 and continue until Q1 2029.

Tesla is identified in the delivery pathway — but the EPC and LTSA are still to be executed. BBI is not treating them as already awarded or signed contracts.
Blackstone BESS 500MW 2000MWh battery project at Swanbank Queensland entering federal assessment with construction targeted for November 2026
BBI Project Watch — the 500MW / 2,000MWh Blackstone BESS has entered the EPBC process with construction currently targeted from November 2026.
Project Signal Federal referral, a defined commercial close sequence and a near-term construction target.
500MW Power Capacity
2GWh Energy Storage
4hr Storage Duration
275kV Grid Connection
Nov 26 Construction Target
Why this is a genuine delivery story The federal referral does more than describe an environmental approval step. It names the financing, EPC, long-term service, grid connection and Notice-to-Proceed milestones that must line up before a targeted November 2026 construction start.

Blackstone enters the EPBC process at 500MW / 2,000MWh

The Australian Government's EPBC Act Public Portal lists the Blackstone Battery Energy Storage System under referral number 2026/10624.

The project is proposed at 45 Patrick Street, Swanbank, adjacent to the existing Blackstone 275kV Substation.

The federal portal currently lists the project status as Referral Decision – Open for Public Comment. This means the federal process is active; it should not be described as a completed EPBC approval.

The referral describes a standalone 500MW / 2,000MWh BESS, equivalent to four hours of storage at maximum discharge.

The project is being advanced through Blackstone BESS OpCo Pty Ltd, with Octopus Australia identified publicly as the owner/developer behind the project.

The referral sets out a clear pathway from assessment to Notice to Proceed

The strongest commercial element of the new referral is the sequence Octopus has identified for the period following the federal process.

The project still needs to finalise Operational Works approvals with Ipswich City Council, complete project financing and achieve financial close.

It must also execute its planned Tesla EPC and Long-Term Service Agreement arrangements and complete connection and access agreements with Powerlink Queensland.

The referral then identifies financial close and the issue of a Notice to Proceed for construction in Q4 2026.

Blackstone BESS commercial delivery pathway showing financial close Tesla EPC and LTSA Powerlink agreements and Notice to Proceed before construction
The current project pathway places financial close, Tesla contracting, Powerlink agreements and NTP ahead of physical construction.
Pre-construction sequence

The key dependencies are commercial as well as regulatory

This is what makes Blackstone more commercially tangible than a typical early-stage battery referral.

The project is not simply waiting for an environmental decision. Financing, technology delivery, long-term servicing, transmission access and formal construction authorisation are all identified in the near-term pathway.

If those steps align with the current schedule, physical works could commence within months.

Tesla is identified for EPC and long-term service — but execution remains ahead

The EPBC referral explicitly states that the project intends to execute the Engineering, Procurement and Construction contract and Long-Term Service Agreement with Tesla.

That wording is commercially important.

It identifies Tesla as the intended counterparty for two critical parts of the delivery model, but it does not say the EPC contract or LTSA has already been executed.

BBI contract position: Tesla should be described as the identified or intended EPC/LTSA counterparty based on the federal referral. BBI is not describing Tesla as having already received an executed EPC award unless a subsequent primary source confirms signature of those agreements.

The distinction matters because execution of the Tesla agreements sits alongside financial close, Powerlink agreements and NTP in the project's remaining pre-construction sequence.

November construction would open a broad civil, electrical and high-voltage work program

Construction is currently expected to commence in November 2026 and continue until Q1 2029.

The referral describes considerably more than battery-container installation. The physical scope extends across site preparation, civil infrastructure, mine remediation, high-voltage works and commissioning.

Select the workstreams below to see what the federal referral currently identifies.

Clearing and grading, site preparation, bulk earthworks, access roads, driveways, stormwater infrastructure and temporary construction compounds.
Mine remediation works are identified for historical underground mining tunnels within the eastern part of the project site.
Construction includes a new 275kV substation and high-voltage underground cables connecting the facility to the existing Blackstone Substation.
Delivery and installation of battery units, transformers, switchgear, cables, earthing systems and associated electrical infrastructure.
The construction program includes establishment and operation of a temporary concrete batching plant.
The project scope extends through testing, commissioning, energisation and final demobilisation of the construction workforce.
Contractor relevance

The construction scope reaches from remediation and earthworks to 275kV energisation

Blackstone's industrial-site history creates a delivery task that extends beyond standard battery installation.

Contractors could ultimately be required across geotechnical work, mine remediation, civil construction, drainage, concrete, high-voltage electrical systems, cabling, earthing, equipment installation, logistics and commissioning.

These are identified physical project workstreams, but BBI has not identified a public Blackstone-specific subcontract package register. They should not be treated as confirmed open tenders unless later procurement notices are released.

Blackstone BESS construction scope including mine remediation earthworks battery installation new 275kV substation and underground grid connection
BBI contractor watch — Blackstone's referral identifies mine remediation, major civil works, battery installation and new 275kV infrastructure.

Powerlink agreements are another critical pre-construction gate

Blackstone is proposed directly beside the existing Blackstone 275kV Substation, placing the project close to major transmission infrastructure within the Swanbank–New Chum industrial precinct.

The referral says Octopus still intends to execute connection and access agreements with Powerlink Queensland covering the Blackstone Substation extension and installation of high-voltage underground cables.

Powerlink's own southern Queensland planning material has previously shown Blackstone BESS connection applications in the Moreton zone.

The same Blackstone Substation area already plays an important role in the wider Swanbank energy precinct. Powerlink completed the connection works for CleanCo's separate 250MW Swanbank BESS, which was energised in October 2025.

That project should not be confused with Octopus Australia's Blackstone BESS, but it demonstrates the strategic role of the existing 275kV network in supporting large-scale storage around Swanbank.

The current federal scope is 2GWh — double the energy capacity of the earlier approved configuration

Blackstone has been in development for several years, but the published capacity has changed.

Ipswich City Council and the State Assessment and Referral Agency approved the project in June 2024 under an earlier configuration widely described as 500MW / 1,000MWh.

Blackstone's existing project website still refers to a one-gigawatt-hour battery.

The new federal referral, however, describes the proposed action as 500MW / 2,000MWh.

BBI scope position: the September 2026 EPBC referral is the newest formal project document reviewed and is therefore being used for the current 2GWh project scope. Older 1GWh references relate to the earlier configuration and should not be used as the current storage capacity.

At 500MW of power and 2,000MWh of stored energy, the current proposal represents a nominal four-hour battery configuration.

No reliable current total project CAPEX was identified in the primary sources reviewed, so BBI is not attaching a speculative dollar value to the project.

For comparison, BBI is already tracking other major Queensland battery builds including the 2.4GWh Smoky Creek and Guthrie's Gap battery program, the Fraser Coast Hybrid Project now in construction and APA's Sybella Creek solar and battery investment near Mount Isa.

Confirmed now versus the next commercial gates

Confirmed now
  • Blackstone BESS has entered the EPBC referral process.
  • The current referred scope is 500MW / 2,000MWh.
  • The project is adjacent to the Blackstone 275kV Substation.
  • State/local development approval was obtained in 2024.
  • Tesla is identified as the intended EPC/LTSA counterparty.
  • Powerlink connection and access agreements are identified in the next-step pathway.
  • Construction is currently targeted to commence in November 2026.
  • Construction completion and operations are targeted for Q1 2029.
Blackstone BESS project pathway from EPBC assessment through financial close Tesla and Powerlink agreements Notice to Proceed November 2026 construction and Q1 2029 operations
BBI delivery pathway — federal assessment is active now, with financial close, contract execution and NTP required before the targeted construction start.
Contractor watch

The next signals could arrive quickly if the November program is maintained

Blackstone's schedule leaves relatively little space between the present federal process and the targeted start of construction.

That makes financial close, Tesla contract execution, Powerlink agreements and NTP particularly important milestones for Queensland's battery and electrical contracting market.

If those conditions are achieved, the project would move rapidly from development into a multi-year civil, electrical and high-voltage build.

What BBI will watch next

Federal EPBC referral decision
Ipswich Operational Works approvals
Blackstone financial close
Tesla EPC contract execution
Tesla Long-Term Service Agreement execution
Powerlink connection and access agreements
Q4 2026 Notice to Proceed
November construction mobilisation
Sources and primary references
  1. Australian Government EPBC Act Public Portal — Construction and Operation of the Blackstone Battery Energy Storage System, EPBC 2026/10624
  2. Blackstone Battery — Project timeline and June 2024 development approval
  3. Blackstone Battery — Project information
  4. Powerlink Queensland — Southern Queensland transmission update
  5. Energy-Storage.news — Octopus Australia refers 2GWh Blackstone BESS for EPBC Act assessment, 8 September 2026
Disclaimer: Bowen Basin Index provides project, procurement and industry information based on publicly available information current at the date of publication. The Blackstone BESS is currently in the EPBC referral process and has not been represented by BBI as having received final federal environmental approval. The current federal referral identifies Tesla as the intended counterparty for an EPC contract and Long-Term Service Agreement, but states that those agreements are still to be executed; BBI therefore does not describe them as completed contract awards. Connection and access agreements with Powerlink Queensland, financial close, Operational Works approvals and Notice to Proceed also remain future project gates. Construction commencing in November 2026 and operations commencing in Q1 2029 are current project targets and remain conditional. The current federal referral specifies 500MW / 2,000MWh, while older project information refers to the previous 500MW / 1,000MWh configuration. No reliable current total project CAPEX was identified in the primary sources reviewed.